CAPITAL IMPROVEMENTS
PROGRAM
ADOPTED
FISCAL 2026-2031
_____________________________________________
Adopted by the Cape Girardeau City Council in the State of
Missouri on March 16, 2026. The program serves as a guideline
for major one-time expenditures by the City. For standard,
recurring expenses, please see the 2026-2027 Annual Budget.
2026
1
FY 2026‐2031 Capital Improvement Program
10 Year Projection
CIP SUMMARY
FY 2026‐2031
Recurring / Grant Revenue Projects FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
ADMINISTRATIVE SERVICES 4,340$ 12,250$ 6,000$ 6,000$ 66,000$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 30,000$ ‐$124,590$
CAPE GIRARDEAU REGIONAL AIRPORT 14,650,000$ 1,650,000$ 8,397,500$ ‐$‐$‐$‐$‐$‐$‐$‐$3,609,000$ 28,306,500$
FIRE DEPARTMENT 233,914$ 65,046$ ‐$65,000$ ‐$‐$‐$‐$‐$‐$‐$‐$363,960$
PARKS & RECREATION 135,000$ 450,000$ 425,000$ 15,200,000$ ‐$‐$‐$‐$‐$‐$‐$5,026,000$ 21,236,000$
PUBLIC WORKS 6,400,000$ 20,500,000$ 8,315,638$ 2,847,500$ 4,752,854$ 2,900,000$ 17,333,833$ ‐$‐$‐$20,233,833$ 43,450,000$ 106,499,825$
Department Total by Fiscal Year 21,423,254$ 22,677,296$ 17,144,138$ 18,118,500$ 4,818,854$ 2,906,000$ 17,339,833$ 6,000$ 6,000$ 6,000$ 20,263,833$ 52,085,000$ 156,530,875$
Tax Initiative Projects FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
CAPITAL IMPROVEMENT SALES TAX 1,457,500$ 2,001,000$ 1,384,000$ 1,398,500$ 1,413,200$ 1,428,500$ 1,445,000$ 1,030,000$ 530,000$ ‐$4,433,500$ ‐$12,087,700$
PARKS & STORMWATER TAX 1,200,000$ 2,921,069$ 1,460,228$ 3,203,931$ 2,910,717$ 300,000$ 300,000$ 300,000$ 300,000$ ‐$1,200,000$ ‐$12,895,945$
PUBLIC SAFETY TRUST FUND 670,645$ 195,052$ 2,395,704$ 1,550,779$ 164,704$ 1,408,752$ 1,408,752$ 8,752$ 1,408,752$ 8,752$ 4,243,760$ ‐$9,220,644$
TRANSPORTATION TRUST FUND 8,300,000$ 6,800,000$ 6,800,000$ 2,300,000$ 2,300,000$ ‐$‐$‐$‐$‐$‐$2,000,000$ 28,500,000$
Tax Initiative Total by Fiscal Year 11,628,145$ 11,917,121$ 12,039,932$ 8,453,210$ 6,788,621$ 3,137,252$ 3,153,752$ 1,338,752$ 2,238,752$ 8,752$ 9,877,260$ 2,000,000$ 62,704,289$
CIP Project Total by Fiscal Year 33,051,399$ 34,594,417$ 29,184,070$ 26,571,710$ 11,607,475$ 6,043,252$ 20,493,585$ 1,344,752$ 2,244,752$ 14,752$ 30,141,093$ 54,085,000$ 219,235,164$
Unfunded Project Total by Fiscal Year 10,289,650$ 2,250,000$ 656,000$ 16,700,000$ 1,995,368$ 1,400,000$ 1,400,000$ ‐$1,400,000$ ‐$4,200,000$ 8,635,000$ 44,726,018$
FY26‐31 CIP Summary 2
FY 2026‐2031 Capital Improvement Program
10 Year Projection
ADMINISTRATIVE SERVICES
FY 2026‐2031
Map ID #Capital Assets ‐ IT Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
Tyler Resident Access ‐ Module Implementation
General Fund /
Utilities Development
City currently utilizes Tyler Citizen Self Service (CSS) for citizens to
access utilities, licenses and permits. CSS is at end of life and
customers are being migrated to an updated Tyler Technologies
module called Resident/Utilities Access to replace the current CSS
and provide enhanced functionality for online applications,
permitting licensing, scheduling and utility registration and
payment. Only cost will be one time implementation. Annual
fees will remain the same.4,340$ ‐$ 4,340$
Records Request Management Software General Fund
Program will (1) reduce workload by automatically deflecting,
merging duplicate requests, and utilizing trending topics with auto‐
follow; (2) Work faster by automating repetitive tasks using
custom‐configured, best practice templates and workflows for
notifications, escalations, tracking and reporting; (3) Gain control
with pst. email extraction/de‐duplication, redaction oops
protection, and a defensible audit trail.10,000$ ‐$ 10,000$
Advisory Board Management Software Module for
Granicus System Innovation Fund General Fund
Granicus Peak Board Agenda Management was purchased in 2024
to replace obsolete Novus Agenda Management System. This is
an add‐on module to track and manage advisory boards, including
on‐line application, vacancies, membership and terms,
attendance, demographics, appointment notifications, etc.
Provide for better tracking and management of boards, savings
staff time to manually track, in separate programs, applications,
rosters, attendance and notifications.2,250$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 30,000$ 50,250$
Website Redesign Innovation Fund General Fund
Redesign of website to coincide with Comp Plan/Strategic Plan/Re‐
Branding. Standard public practice to redesign web site every 3‐5
years.60,000$ ‐$ 60,000$
Capital Assets ‐ IT Projects' Totals by Fiscal Year 4,340$ 12,250$ 6,000$ 6,000$ 66,000$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 30,000$ ‐$ 124,590$
CIP Project Total by Fiscal Year 4,340$ 12,250$ 6,000$ 6,000$ 66,000$ 6,000$ 6,000$ 6,000$ 6,000$ 6,000$ 30,000$ ‐$ 124,590$
Unfunded Project Total by Fiscal Year ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$
ADMINISTRATIVE SERVICES 3
8
67
4
9
3
5
Tax
i
w
a
y
C
A1
Taxiway F
Ta
x
i
w
a
y
B
Taxiway C
T
a
x
i
w
a
y
E
Taxiway A
Tax
i
w
a
y
D
Run
w
a
y
2
/
2
0
Taxiway A
Runway 10/
2
85 8
5
2
1
CIP FY 2026-2031Cape GirardeauRegional Airport
µ
0 1,000 2,000 Feet
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:12,855
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
Transportation Projects
Transportation Projects
Capital Assets
Capital Assets
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
4
FY 2026‐2031 Capital Improvement Program
10 Year Projection
CAPE GIRARDEAU REGIONAL AIRPORT
FY 2026‐2031
Map ID #Capital Assets ‐ Facilities Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
1 Air Traffic Control Tower (ATCT)Unfunded
New control tower in a new location. Current one was built in
1973, leaks when it rains, windows have lost vacuum so foggy.
Many of the interior structure components are very rusty, need to
b e checked by an engineer. Costly to maintain and keep in
working condition. With the increased aircraft traffic and poor
working conditions the safety of the aircraft are a major concern.8,000,000$ ‐$ 8,000,000$
2 New Fuel Farm Unfunded
TOP PRIORITY ‐ New Fuel farm which will include two 20,000
gallon tanks that will increase capacity. A new farm will also bring
the facility up to current safety standards. Current farm is
becoming very costly to maintain and is having issues with water
getting into the fuel. The FAA, Military, Titan and State inspectors
all agree that the farm needs to be replaced.1,500,000$ ‐$ 1,500,000$
3 Snow Removal Equipment Storage Building Unfunded
Snow Removal Equipment (SRE) Storage Building (56' x 40'). FAA
recommends a storage facility especially if the equipment was
purchased with federal funds. The building, using shipping
containers in the construction would allow for additional storage
of seasonal equipment. Estimated material cost = 54K.150,000$ ‐$ 150,000$
5 Security / Wildlife Perimeter Fence Unfunded Casino
Security / wildlife perimeter fence is not only needed for security
and wildlife prevention, it will be required by the TSA / FAA when
aircraft having capacity over 61 seats operate out of CGI.1,500,000$ ‐$ 1,500,000$
6
Cape Aviation ‐ Exterior Painting & Roof
Maintenance Unfunded
Paint the outside of Cape Aviation and perform maintenance on
the roof. 2007 was the last time the building was painted. Cape
Aviation is the face of the airport for the corporate / private
aircraft that use CGI.150,000$ ‐$ 150,000$
Aircraft Rescue Firefighting (ARFF) Access Road Eligible for MoDOT Access road to airport ARFF facility ‐$ 750,000$ 750,000$
Feasibility Study for Air Traffic Control Tower Unfunded Feasibility study for remodel/move of Air Traffic Control Tower.‐$ 100,000$ 100,000$
Capital Assets ‐ Facilities Projects' Totals by Fiscal Year 9,650,000$ 1,650,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 850,000$ 12,150,000$
Map ID #Transportation Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
4
Taxiways Echo & Foxtrot Reconstruction and
Lighting Upgrades AIP / BIL Unfunded, 5% Taxiways Echo & Foxtrot reconstruction (95%/5%)5,000,000$ ‐$ 5,000,000$
7 Taxiway Alpha Rehabilitation AIP Taxiway Alpha Rehabilitation 7,700,000$ ‐$ 7,700,000$
8 Airfield Pavement Maintenance AIP Crack seal 75,000LF of airfield surfaces and general aviation ramp 510,000$ ‐$ 510,000$
9 Pave Airport Parking Lot and Access Road MoDOT Parking lot and access road pavements 187,500$ ‐$ 187,500$
Access Road and Taxilane for NW State Funding / CNT Unfunded Landside access road and airside taxilane for NW quad, parcels ‐$ 1,323,000$ 1,323,000$
Taxiway Access to NW Quadrant MoDOT ($750,000)
Private Partnership /
CNT Taxiway Access to NW Quadrant ‐$ 1,000,000$ 1,000,000$
Land Acquisition for Runway 10 Extension MoDOT / CNT Land Acquisition for Runway 10 Extension ‐$ 436,000$ 436,000$
Transportation Projects' Totals by Fiscal Year 5,000,000$ ‐$ 8,397,500$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 2,759,000$ 16,156,500$
CIP Project Total by Fiscal Year 14,650,000$ 1,650,000$ 8,397,500$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 3,609,000$ 28,306,500$
Unfunded Project Total by Fiscal Year 9,650,000$ 1,650,000$ ‐$ ‐$ ‐$ ‐$ 3,609,000$ 14,909,000$
CAPE GIRARDEAU REGIONAL AIRPORT 5
13
2
3
3
4
3
CIP FY 2026-2031Fire Dept.
µMissi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
Capital Assets
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
6
FY 2026‐2031 Capital Improvement Program
10 Year Projection
FIRE DEPARTMENT
FY 2026‐2031
Map ID #Capital Assets ‐ Facilities Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
1 Fire Station #1 ‐ Garage Door Replacement CIST
This request would replace the 8 remaining garage doors that are
not energy efficient and no longer manufactured.120,000$ ‐$ 120,000$
2 Fire Station #1 ‐ Parking Lot Improvements Unfunded
This replaces the current broken concrete in the parking lot and
paves the current gravel parking lot. Area of approx. 20,000 sq ft.75,000$ ‐$ 75,000$
4 Fire Station #2 ‐ Garage Door Replacement CIST
This request would replace the 4 remaining garage doors that are
not energy efficient and no longer manufactured.65,000$ ‐$ 65,000$
Capital Assets ‐ Facilities Projects' Totals by Fiscal Year 195,000$ ‐$ ‐$ 65,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 260,000$
Map ID #Capital Assets ‐ IT Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
3 PIXIS ‐ Medical Supply Inventory Control System Unfunded
This adds a Medical Inventory Control Systems for each of the
four fire stations in our department. This will assist in better
tracking on the use of medications, bandaging, airway supplies,
and diabetic supplies to reduce expenditures. It also allows for
internal controls to be set which comply with state and federal
regulations.38,914$ 65,046$ ‐$ 103,960$
Capital Assets ‐ IT Projects' Totals by Fiscal Year 38,914$ 65,046$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 103,960$
CIP Project Total by Fiscal Year 233,914$ 65,046$ ‐$ 65,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 363,960$
Unfunded Project Total by Fiscal Year 113,914$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 113,914$
FIRE DEPARTMENT 7
53
4
1
2
CIP FY 2026-2031Parks & RecreationDepartment
µ
Missi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
Capital Assets
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
8
FY 2026‐2031 Capital Improvement Program
10 Year Projection
PARKS AND RECREATION
FY 2026‐2031
Map ID #Capital Assets ‐ Facilities Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
1 Replace Capaha Field Scoreboard Unfunded
This project will include replacement of the scoreboard at Capaha
Field. The City will pay 45% of the replacement cost.135,000$ ‐$ 135,000$
2 Replace Capaha Field Turf Unfunded
This project will include replacement of the artificial turf at
Capaha Field. The City will pay 45% of the replacement cost.450,000$ ‐$ 450,000$
3
Osage Centre ‐ Replace gym floor with wood
flooring Unfunded Replace the original tile floor in the gym 425,000$ ‐$ 425,000$
4 Expand the Sportsplex Facility to the Northwest Unfunded
Expansion of the Northwest side of the Sportsplex to include
more playing fields/courts. This expansion will allow the facility to
accomodate larger events and have a positive affect on the local
economy. 15,000,000$ ‐$ 15,000,000$
5 Refurbish Slides at Cape Splash Unfunded
The original small and medium slides at Cape Splash will need to
be refurbished and gel coat applied.200,000$ ‐$ 200,000$
Shawnee Park Center ‐ Generator Unfunded
Addition of a generator to the facility will provide access to City
services during times of power outages and disaster ‐$ 420,000$ 420,000$
Jaycee Golf Course ‐ Expansion and Renovation of
the Pro Shop Unfunded
The Golf Course Pro Shop is in need of a renovation and expanded
office and concession area.‐$ 300,000$ 300,000$
Shawnee Park Sports Complex ‐ Extend Concession
Patio Unfunded 40' Extension off of West side of Concession Building A ‐$ 192,000$ 192,000$
Kiwanis Park Improvements Unfunded Grant Roadway system and sidewalk additions ‐$ 50,000$ 50,000$
Capital Assets ‐ Facilities Projects' Totals by Fiscal Year 135,000$ 450,000$ 425,000$ 15,200,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 962,000$ 17,172,000$
Map ID #Transportation Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
Kiwanis Park ‐ Roadway Unfunded
Pave the road leading to Shelter #4 in Kiwanis Park that is
currently gravel ‐$ 200,000$ 200,000$
Arena Park ‐ Fields #9 ‐ #10 Roadway Unfunded
Overlay the road between fields #9 and #10 and improve the
storm water drainage ‐$ 450,000$ 450,000$
Shawnee Park Center ‐ Parking Lot Unfunded
Overlay parking lot servicing the Shawnee Park Center and upper
Shawnee Park Sports Complex fields ‐$ 200,000$ 200,000$
Arena Park ‐ Streets and Parking Lots Unfunded Overlay the internal streets and parking lots in Arena Park ‐$ 750,000$ 750,000$
Dennis Scivally Park ‐ Parking Lot and Road Unfunded Overlay parking lot and road in Dennis Scivally Park ‐$ 200,000$ 200,000$
Osage Park ‐ Overflow Parking Lot Unfunded
Overlay the parking lot south of the Osage Centre that serves as
overflow for Cape Splash and the Community Centre ‐$ 500,000$ 500,000$
Shawnee Park ‐ Soccer Field Parking Unfunded
Overlay the parking lots at the lower and West End Blvd soccer
fields. ‐$ 400,000$ 400,000$
Cape Splash ‐ Parking Lot Unfunded
Overlay the primary parking lot servicing Cape Splash in Osage
Park.‐$ 200,000$ 200,000$
Capaha Park ‐ Upper Parking Lot Unfunded Overlay upper parking lot by the Baseball Stadium in Capaha Park ‐$ 230,000$ 230,000$
Jaycee Municipal Golf Course Overlay Unfunded Repair and overlay approx. 65,000 SF of parking areas and road ‐$ 230,000$ 230,000$
Red House Parking Area Unfunded Improvement to parking area north of Red House ‐$ 81,000$ 81,000$
Arena Park ‐ Pave Maintenance Building Parking
Lots Unfunded
Pave the Arena Park maintenance building parking lots that are
currently gravel ‐$ 250,000$ 250,000$
Capaha Park ‐ Roadways Unfunded Overlay the roads in Capaha Park ‐$ 200,000$ 200,000$
Bloomfield Trail Parking Lot Unfunded Parking Lot for Bloomfield Trail ‐ Acquire Land ‐$ 173,000$ 173,000$
Transportation Projects' Totals by Fiscal Year ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 4,064,000$ 4,064,000$
CIP Project Total by Fiscal Year 135,000$ 450,000$ 425,000$ 15,200,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 5,026,000$ 21,236,000$
Unfunded Project Total by Fiscal Year 135,000$ 450,000$ 425,000$ 15,200,000$ ‐$ ‐$ 5,026,000$ 21,236,000$
PARKS AND RECREATION 9
2
15
8
9
3
106
7
11
4
CIP FY 2026-2031Public Works Dept
µ
Missi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
Capital Assets
Environmental Projects
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
10
FY 2026‐2031 Capital Improvement Program
10 Year Projection
PUBLIC WORKS
FY 2026‐2031
Map ID #Capital Assets ‐ Facilities Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
2 Recycling Center / Solid Waste Shed Paving Solid Waste Fund
Pave an area that is currently gravel. This area is used daily by the
recycle center and the trash trucks.200,000$ ‐$ 200,000$
Capital Assets ‐ Facilities Projects' Totals by Fiscal Year 200,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 200,000$
Map ID #Capital Assets ‐ Non‐fleet Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
1 2) Addition of Primary SCU‐4 & Secondary SSB‐4 Water Fund Cape Rock Water Treatment Facility 600,000$ 8,305,000$ ‐$ 8,905,000$
5 a. Booster Pump for Carbonic Acid Water Fund Cape Rock Water Treatment Facility 125,000$ ‐$ 125,000$
6 b. Stabilization Tank Addition Water Fund Cape Rock Water Treatment Facility 560,000$ ‐$ 560,000$
7 c. Aerator Bypass Improvements Water Fund Cape Rock Water Treatment Facility 610,000$ ‐$ 610,000$
3 Meadowbrook Standpipe Booster Pump Station Water Fund Improvements to existing 1,900,000$ ‐$ 1,900,000$
8 College Booster Pump Stations Water Fund College Booster Pump Stations 3,000,000$ 3,000,000$
9 Gordonville Tank Booster Pump Station Water Fund Gordonville Tank Booster Pump Station 2,530,638$ 2,530,638$
11 LaSalle Standpipe Booster Pump Station Water Fund LaSalle Standpipe Booster Pump Station 2,052,854$ 2,052,854$
High Priority Watermain Improvements Water Fund City‐wide, per the 2022 WSFP 4,900,000$ 2,500,000$ 2,600,000$ 2,700,000$ 2,900,000$ 3,000,000$ 5,900,000$ 18,600,000$
10 New Maintenance Shop Water Fund Replacement of existing 285,000$ ‐$ 285,000$
Converson to Sodium Hypochlorite Water Fund Cape Rock Water Treatment Facility 3,833,833$ 3,833,833$ 3,833,833$
Filter Rehab Water Fund Cape Rock Water Treatment Facility 10,500,000$ 10,500,000$ 10,500,000$
Medium Priority Watermain Improvements Water Fund City‐wide, per the 2022 WSFP ‐$ 42,450,000$ 42,450,000$
Plant 1 Residuals Water Fund Solids handling improvements at Plant 1 ‐$ 1,000,000$ 1,000,000$
Capital Assets ‐ Non‐fleet Projects' Totals by Fiscal Year 2,500,000$ 17,500,000$ 5,315,638$ 2,600,000$ 4,752,854$ 2,900,000$ 17,333,833$ ‐$ ‐$ ‐$ 20,233,833$ 43,450,000$ 96,352,325$
Map ID #Environmental Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
I&I Program ‐ Cured‐In‐Place‐Pipe Repairs Sewer Fund
Rehab of sewer system piping and manholes to reduce the rain
water intrusion into the sewer system.3,000,000$ 3,000,000$ 3,000,000$ ‐$ 9,000,000$
4
Odor Control Media Replacement at WWTF and
One Lift Station Sewer Fund
Change out odor control media at WWTF and one lift station using
design engineer's preferred provider to keep odors to a minimum.
The media is changed every 3 years. As flow increases or
conditions change, frequency may need to be updated. The 2029
amount was estimated at 10 percent higher than the 2026
amount.225,000$ 247,500$ ‐$ 472,500$
Environmental Projects' Totals by Fiscal Year 3,225,000$ 3,000,000$ 3,000,000$ 247,500$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 9,472,500$
Map ID #Transportation Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
Traffic Signal Upgrades Motor Fuel Tax
Upgrade the communication equipment and safety features at 16
City‐operated traffic signals. The current equipment is obsolete
and we can no longer obtain parts. We have successfully
upgraded 6 traffic signals to date.475,000$ ‐$ 475,000$
Transportation Projects' Totals by Fiscal Year 475,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 475,000$
CIP Project Total by Fiscal Year 6,400,000$ 20,500,000$ 8,315,638$ 2,847,500$ 4,752,854$ 2,900,000$ 17,333,833$ ‐$ ‐$ ‐$ 20,233,833$ 43,450,000$ 106,499,825$
Unfunded Project Total by Fiscal Year ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$
PUBLIC WORKS 11
1
CIP FY 2026-2031Capital ImprovementSales Tax
µMissi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
CIST Project
CIST project
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
12
FY 2026‐2031 Capital Improvement Program
10 Year Projection
CAPITAL IMPROVEMENT SALES TAX (CIST)
FY 2026‐2031
Map ID #CIST Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
2" Line Replacement CIST Replace 2" lines with 6" water lines City‐wide $ 130,000 $ 130,000 $ 130,000 $ 130,000 $ 130,000 $ 130,000 $ 130,000 $ 130,000 $ 130,000 520,000$ 1,170,000$
Water Tank Asset Management Program CIST Annual USG water tank asset management program 400,000$ 400,000$ 400,000$ 400,000$ 400,000$ 400,000$ 400,000$ 400,000$ 400,000$ 1,600,000$ 3,600,000$
Annual CIST Street Repair CIST Annual CIST street maintenance and repair program 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 500,000$ 1,500,000$ 4,000,000$
Lead Service Line Replacement
Federal / State
Grants CIST 7% replacement from main to house every year 327,500$ 341,000$ 354,000$ 368,500$ 383,200$ 398,500$ 415,000$ 813,500$ 2,587,700$
1 SCADA Improvements CIST Cape Rock Water Treatment Facility 100,000$ 630,000$ ‐$ 730,000$
CIST Projects' Totals by Fiscal Year 1,457,500$ 2,001,000$ 1,384,000$ 1,398,500$ 1,413,200$ 1,428,500$ 1,445,000$ 1,030,000$ 530,000$ ‐$ 4,433,500$ ‐$ 12,087,700$
CIP Project Total by Fiscal Year 1,457,500$ 2,001,000$ 1,384,000$ 1,398,500$ 1,413,200$ 1,428,500$ 1,445,000$ 1,030,000$ 530,000$ ‐$ 4,433,500$ ‐$ 12,087,700$
Unfunded Project Total by Fiscal Year ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$
CAPITAL IMPROVEMENT SALES TAX 13
2
9
7
8
63
14
16
15
5
4
1
10
11 12
13
CIP FY 2026-2031Parks & Stormwater Tax 2
µMissi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
PRS2: Parks
PRS2: Parks
PRS2: Stormwater
Cape City Limits
14
FY 2026‐2031 Capital Improvement Program
10 Year Projection
PARKS & STORMWATER TAX (PRS)
FY 2026‐2031
Map ID #PRS2 Projects ‐ Parks Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
1
Shawnee Park Sports Complex Facility and Field
Improvements (Phase 2)PRS2
This project will include upgrading complex lighting to LED,
expansion of the maintenance building, and paving of the
maintenance building parking lot.700,000$ 431,069$ ‐$ 1,131,069$
2 Dennis Scivally Park Restroom PRS2
A permanent restroom will be placed at Dennis Scivally Park. This
will be a prefabricated unit.160,000$ ‐$ 160,000$
3
Asphalt Overlay of Osage Centre and Shawnee Park
Center Parking Lots PRS2
Overlay the main parking lots at the Osage Centre and the
Shawnee Park Center.1,000,000$ ‐$ 1,000,000$
4 Golf Course Enhancements PRS2
The Cape Jaycee Golf Course scheduled replacement / renovation
of the cart and maintenance shop.200,000$ 150,000$ ‐$ 350,000$
5 City Cemeteries PRS2
Improvements to New Lorimier and Fairmount Cemeteries include
construction of a maintenance building and overlay of roadways 250,000$ ‐$ 250,000$
6 Shawnee Park Center Addition PRS2 Expand Shawnee Park Center on the North East side of the facility.100,000$ 550,000$ ‐$ 650,000$
10
Cape LaCroix Recreation Trail Improvements and
Widening (Phase 3)PRS2
This project will include widening and overlay of the trail from the
Osage Centre to Hopper Road, some erosion control and
implementation of a new sign program.610,228$ 653,931$ ‐$ 1,264,159$
11 Cape Splash (Phase 3)PRS2
This project will include updates and renovations to the park and
an added attraction to further appeal to the community.2,000,000$ ‐$ 2,000,000$
12 Walker Park Development PRS2
The newly acquired Walker Park will be developed with available
PRS funds. The development may include a shelter, playground,
off‐street parking and a walking trail. We will be seeking grant
opportunities for the project.250,000$ ‐$ 250,000$
13 Arena Park Master Plan Unfunded
The Arena Park Phased Master Plan will include ADA accessibility
upgrades, and improvements to the park's lighting, electrical and
roadways.1,495,368$ ‐$ 1,495,368$
14 Red Star Development Unfunded
The Red Star Neighborhood Park will be a phased new park
adjacent and part of flood buyout property on the north side of
the City adjacent to the Red Star Boat Ramp with connections to
the River Flood Wall Trail. Improvements include walking trails,
picnic/pavilion areas and playgrounds with the potential for an RV
Campground adjacent to the Casino.500,000$ ‐$ 500,000$
15 Southside Neighborhood Park PRS2
A neighborhood park will be constructed on the southside of Hwy
74 365,349$ ‐$ 365,349$
16 Cape Rock Park Improvements PRS2 Grant
Improve ADA accessibility to the park, improved parking, lighting
and historic representation of the park property.250,000$ ‐$ 250,000$
PRS2 Projects ‐ Parks Totals by Fiscal Year 900,000$ 2,091,069$ 1,160,228$ 2,903,931$ 2,610,717$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 9,665,945$
Map ID #PRS2 Projects ‐ Stormwater Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
Sewer Manhole Rehab PRS2 Repair and rehab of sanitary sewer manholes by contract 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 1,200,000$ 2,700,000$
7 Camellia Drainage Projects PRS2
Upgrade street crossing on Camellia in the 100 block and install
additional piping near 239/244 Camellia (Proj #6237)250,000$ ‐$ 250,000$
8 Trail Creek Bank Improvements ‐ Phase 2 PRS2 Stabilize Cape LaCroix Trail Creek Bank at Walden Park 180,000$ ‐$ 180,000$
9 Cape LaCroix Trail Drainage Improvements PRS2
Lexington trail crossing and trail side flume on Lynwood Hills
bridge (Proj #6261)100,000$ ‐$ 100,000$
PRS2 Projects ‐ Stormwater Totals by Fiscal Year 300,000$ 830,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ ‐$ 1,200,000$ ‐$ 3,230,000$
CIP Project Total by Fiscal Year 1,200,000$ 2,921,069$ 1,460,228$ 3,203,931$ 2,910,717$ 300,000$ 300,000$ 300,000$ 300,000$ ‐$ 1,200,000$ ‐$ 12,895,945$
Unfunded Project Total by Fiscal Year ‐$ ‐$ ‐$ ‐$ 1,995,368$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 1,995,368$
PARKS STORMWATER TAX 15
6
8
7 14
2
3
5
CIP FY 2026-2031Public SafetyTrust Fund
µMissi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
PSTF Project
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
16
FY 2026‐2031 Capital Improvement Program
10 Year Projection
PUBLIC SAFETY TRUST FUND (PSTF)
FY 2026‐2031
Map ID #PSTF Projects ‐ Fire Department
Planning funding
source
Other Funding
Source Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
Replace Self Contained Breathing Apparatus (SCBA) Unfunded
This replaces the current SCBA in use on the front line apparatus
due to continued critical failures of SCBA face pieces, high
pressure hoses, buckles, and confined spaced rescue escape
packs.210,000$ 150,000$ 150,000$ 100,000$ ‐$ 610,000$
Foam Replacement Unfunded
This replaces the current foam throughout the department that
contains polyfluoroalkyl substances (PFAS) chemicals. 75,000$ ‐$ 75,000$
Replace Front Line Cardiac Monitor / Defibrillators Grant PSTF / Health Fund
Replace front line cardiac monitors / defibrillators at the end of
their life cycle.66,000$ ‐$ 66,000$
Double Stack Boat Trailers Unfunded
This replaces 2 of our current converted boat trailers with 2
double stack boat trailers. 55,516$ ‐$ 55,516$
Replace Boat Motors Unfunded
This project funds the replacement of the current boat motors
that were donated about 2008. The current boat motors are
obsolete and no longer manufactured.50,220$ ‐$ 50,220$
6 Replace Ladder 1 Unit 243 PSTF Casino
Replace the 2017 ladder truck at the end of its life cycle for front
line service.2,000,000$ ‐$ 2,000,000$
7 Fire Station #4 ‐ Renovations and Repair Unfunded General Fund
Renovations and repairs to FS #4: enclose gear storage, remodel
bunk room.81,000$ ‐$ 81,000$
8 Replace Engine 4 Unit 257 Unfunded
Replace the 2017 pumper at the end of its life cycle for front line
service.1,400,000$ ‐$ 1,400,000$
Replace Engine 3 Unit 262 Unfunded
Replace the 2017 pumper at the end of its life cycle for front line
service.1,400,000$ 1,400,000$ 1,400,000$
Replace Engine 1 Unit 260 Unfunded
Replace the 2017 pumper at the end of its life cycle for front line
service.1,400,000$ 1,400,000$ 1,400,000$
Replace Rescue 1 Unit 233 Unfunded
Replace the 2017 pumper at the end of its life cycle for front line
service.1,400,000$ 1,400,000$ 1,400,000$
PSTF Projects ‐ Fire Department Totals by Fiscal Year 456,736$ 150,000$ 2,231,000$ 1,500,000$ ‐$ 1,400,000$ 1,400,000$ ‐$ 1,400,000$ ‐$ 4,200,000$ ‐$ 8,537,736$
Map ID #PSTF Projects ‐ Police Department Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
GETAC Body Cam Cloud Storage PSTF
Casino / General
Revenue
The cost of storing crucial footage from officers' body worn
cameras continues to climb each year, but the preservation of this
footage is crucial in both criminal cases and civil cases where the
city might be exposed to liability.119,652$ 119,652$ 119,652$ ‐$ 358,956$
Additional Flock Cameras PSTF / CIST Casino
Adding 10 additional Flock Automated License Plate Readers, in
locations that curently have inadequate coverage would greatly
enhance the department's ability to capture evidentiary footage
of suspect / victim vehicles, aiding in the department's ability to
solve crime, find missing / endangered individuals, and enhance
public safety.45,200$ 36,300$ 36,300$ 36,300$ 36,300$ ‐$ 190,400$
Software for Cell Phone Investigations PSTF Casino
The forensic analysis of cell phone data can provide crucial
evidence in identifying suspects in a crime. Our current forensic
phone data investigations require several pieces of software that
must be updated/renewed each year. Due to the lengthly
description and capabilities of each item, I have included the
written requests from the forensic cell phone investigator to
provide a better understanding of each item.14,800$ ‐$ 14,800$
1 Prepared 911 AI Services PSTF Casino
Prepared is an AI powered emergency communications platform
that turns 911 calls into actionable intelligence and enables faster
responses. This software has the ability to take a 911 call and
transcribe it immediately, which allowa for a more complete,
accurate and faster response, as it can complete this task much
faster than the call taker can type. Additionally, if the system
detects the caller is speaking a language other than English, the
program automatically communicates with the caller in their
native language, then translates their words back to English for
the communicator.10,952$ 8,752$ 8,752$ 8,752$ 8,752$ 8,752$ 8,752$ 8,752$ 8,752$ 8,752$ 43,760$ 89,720$
PUBLIC SAFETY TRUST FUND 17
FY 2026‐2031 Capital Improvement Program
10 Year Projection
2 Firearms Range Lighting PSTF
With the recent improvements to the Police Department Firearms
Training Range, we are requesting a lighting system to improve
the functionality and safety of the Firearms Range. This project
would add permanent, purpose built lighting along the firing lines
and also downrange, which will allow the ability to safely
illuminate shooting positions, targets and the key safety zones of
the range while in use.7,859$ ‐$ 7,859$
3 Exterior Police Department Cameras PSTF Casino
The current cameras lack optical zoom, clarity and smart tracking
capabilities required for high quality evidence. This camera
upgrade will improve video quality, reliability, and coverage,
which is necessary for safety, accountability and evidence
integrity.7,321$ ‐$ 7,321$
4 Communicator Chairs PSTF
There are 6 consoles at our Communications Division. At times, all
6 of these chairs are being used at one time and at least half of
these 6 chairs are being used 24 hours a day, 7 days a week.
Obviously, these chairs are used heavily, and due to this usage,
"regular" chairs that are bought "off the shelf," don't last more
than a year or so, as we have, in the past, purchased this type and
they did not last very long. Additionally, these chairs are about 1/4
of the price of the heavy duty chairs we are requesting. The 3
chairs we are requesting have a full 6 year warranty.5,727$ 5,727$ ‐$ 11,454$
5 Computer Upgrade for Evidence Division PSTF Casino
The current computers provided through the IT Department are
inadequate for processing video evidence efficiently, resulting in
very lengthy times in creating evidentiary videos for prosecutors
and defense attorneys.2,398$ ‐$ 2,398$
PSTF Projects ‐ Police Department Totals by Fiscal Year 213,909$ 45,052$ 164,704$ 50,779$ 164,704$ 8,752$ 8,752$ 8,752$ 8,752$ 8,752$ 43,760$ ‐$ 682,908$
CIP Project Total by Fiscal Year 670,645$ 195,052$ 2,395,704$ 1,550,779$ 164,704$ 1,408,752$ 1,408,752$ 8,752$ 1,408,752$ 8,752$ 4,243,760$ ‐$ 9,220,644$
Unfunded Project Total by Fiscal Year 390,736$ 150,000$ 231,000$ 1,500,000$ ‐$ 1,400,000$ 1,400,000$ 1,400,000$ 4,200,000$ ‐$ 6,471,736$
PUBLIC SAFETY TRUST FUND 18
5
4
2
3
1
CIP FY 2026-2031Transportation Trust Fund
µMissi
s
s
i
p
p
i
R
i
v
e
r
Illinois
0 1 2 Miles
LEGEND
Date: 2/8/2026
Data Source(s):City of Cape Girardeau Government, MO
1:72,300
Coordinate System: NAD 1983 StatePlane Missouri East FIPS 2401 Feet
Created by: Development Services Teresa Heifner, Alliance Water Resources
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
TTF-6 Tax
TTF-7 Tax
Cape City Limits
___________________________________Layers provided by the City of Cape Girardeau are to be used for vis ual aid onlyand are not guaranteed to be accurate. Thes e layers are not to be us ed for any engineering or design purpose.
Numbers correspond to Map ID # on theCIP spreadsheet.
19
FY 2026‐2031 Capital Improvement Program
10 Year Projection
TRANSPORTATION TRUST FUND (TTF)
FY 2026‐2031
Map ID #TTF6 Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
1 Route K School Corridor Safety Improvements TTF6
Intersection improvements, in cooperation with others,
contribution toward total project cost. $ 500,000 ‐$ 500,000$
3 Bertling ‐ Perryville to Big Bend TTF6 Concrete repair.1,000,000$ ‐$ 1,000,000$
TTF6 Projects' Totals by Fiscal Year 500,000$ 1,000,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 1,500,000$
Map ID #TTF7 Projects Funding Source 1 Funding Source 2 Description FY 26‐27 FY 27‐28 FY 28‐29 FY 29‐30 FY 30‐31 FY 31‐32 FY 32‐33 FY 33‐34 FY 34‐35 FY 35‐36 FY 31‐36 CNT Total
Concrete Repair TTF7 Street, curbs, gutters.1,450,000$ 1,450,000$ 1,450,000$ 1,450,000$ 1,450,000$ ‐$ 7,250,000$
Asphalt Maintenance and Overlay TTF7 Annual asphalt overlay program.600,000$ 600,000$ 600,000$ 600,000$ 600,000$ ‐$ 3,000,000$
Streetscape and Sidewalk ‐ New Connectivity and
Repair TTF7 Streetscape & Sidewalk ‐ New Connectivity and Repair 250,000$ 250,000$ 250,000$ 250,000$ 250,000$ ‐$ 1,250,000$
2
Mount Auburn Road from Hopper Road to
Independence St TTF7 New pavement, new curb and gutter, sidewalk repair $ 5,500,000 ‐$ 5,500,000$
4
Perryville Road from Cape Rock Drive to Perry
Avenue TTF7 Pavement repair, addition of new sidewalk on East Side 3,500,000$ ‐$ 3,500,000$
5 Sprigg Street from William Street to Route 74 TTF7 New pavement, new curb and gutter, sidewalk repair 4,500,000$ ‐$ 4,500,000$
Safety Improvements TTF7 Safety improvements / contingency ‐$ 2,000,000$ 2,000,000$
TTF7 Projects' Totals by Fiscal Year 7,800,000$ 5,800,000$ 6,800,000$ 2,300,000$ 2,300,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 2,000,000$ 27,000,000$
CIP Project Total by Fiscal Year 8,300,000$ 6,800,000$ 6,800,000$ 2,300,000$ 2,300,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ 2,000,000$ 28,500,000$
Unfunded Project Total by Fiscal Year ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$
TRANSPORTATION TRUST FUND 20