HomeMy WebLinkAboutRES.234.02-16-1987 BILL NO. 87-24 RESOLUTION N0. ��
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
ENTER INTO A CONTRACT WITH BLACK & VEATCH,
ENGINEERS-ARCHITECTS, FOR A UTILITIES
FEASIBILITY STUDY
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE GIRARDEAU,
MISSOURI , AS FOLLOWS :
SECTION 1 . The City Manager on behalf of the City of Cape
Girardeau, Missouri , is hereby authorized to enter into a Contract
with Black & Veatch, Engineers-Architects , for a utilities
feasibility study. A copy of said Contract is attached to this
Resolution and made a part hereof .
PASSED AND ADOPTED THIS �� DAY OF � 198� •
i�
�� --- - �C � �f
�
�A.
i�.,7 7 .�f -' ' `'� !'� -
� rancis E. Rhodes , Mayor
ATTEST:
� //� S�GC_..f,�r�5.���'t.f7
Alvin M. Stoverink , City Clerk
CONTRACT FOR ENGINEERING SERVICES
THIS CONTRACT is made by and between the City of Cape Girardeau, Missouri ,
hereinafter called the City, and Black & Veatch, Engineers-Architects,
hereinafter called the Engineer.
SECTION I - SCOPE OF SERVICES
The Citizens Committee established by the City Council desires to determine
the options available to the City under the terms of the current franchise
agreements for water, gas, and electric utilities in the City, scheduled
for renewal April 1988, and/or the feasibility of the possible acquisition
and operation of one or more of the utilities by the City.
The City hereby engages the Engineer to perform engineering services in
connection with the investigation to determine options available to the
City under its current franchise agreements and to determine the feasi-
bility of possible City acquired and operated utility system(s). The
Engineer agrees to perform engineering services as directed by the Citizens
Committee including preliminary investigations, limited inspection of
utility property, engineering studies, and bonding feasibility. A detailed
description of the services to be performed is listed in Appendix A.
SECTION II - COMPENSATION
For the services covered by this contract, the City agrees to pay the
Engineer as set forth below.
A. All services rendered by Black & Veatch personnel in con-
junction with the proposed studies will be billed at payroll
costs times a multiplier of 2.0. Payroll costs are defined
as salaries plus direct payroll overheads of 35 percent.
The maximum amount billed shall not exceed $16,900 without
further authorization.
1
B. All direct expenses, including in part travel and subsis-
' tence away from the Kansas City office, long distance tele-
phone, computer charges, and reproduction will be billed at
out-of-pocket cost.
Black & Veatch will render itemized monthly statements to the City for work
performed and costs incurred during the preceding month. Monthly payments
will be due within 30 days after the statement is received by the City.
SECTION III - CITY' S RESPONSIBILITIES
The City will furnish, as required for the work and not at the expense of
the Engineer, the following items if not currently on file with the
Engineer:
A. All information obtained from Union Electric Company
relevant to the studies;
B. All maps, drawings, records, audits, annual reports, and
other data that are available in the files of the City and
which may be useful in the work involved under this con-
tract;
C. Access to public and private property, as necessary, when
required in conduct of field investigations; and
D. Assistance as may be required to gain access to Union
Electic Company staff and facilities.
SECTION IV - OTHER MATTERS
It is mutually understood and agreed:
A. That the Engineer shall not be liable for delays resulting
from causes beyond the reasonable control of the Engineer;
that the Engineer has made no warranties, expressed or
implied, which are not expressly set forth in this contract,
and that under no circumstances will the Engineer be Liable
for indirect or consequential damages.
2
IN WITNESS WHEREOF, the parties have executed this contract on this
day of 19_
CITY OF CAPE GIRARDEAU, MISSOURI
By
Gary A. Eide, City Manager
Attest:
BLACK � VEATCH, Engineers-Architects
By
Ronald D. Hardten, Partner
3
CITY OF CAPE GIRARDEAU, MISSOURI
FRANCHISE REQUIREMENTS AND/OR ACQUISITIONS
OF ELECTRIC, GAS, AND WATER UTILITIES
APPENDIX A
TO
CONTRACT FOR ENGINEERING SERVICES
DESCRIPTION OF SCOPE OF SERVICES
A. Utility Acquisition Study
1. Make the necessary limited inspection of existing utility proper-
ties and assess the condition thereof.
2. Discuss with Union Electric (UE) the operation and condition of
the properties.
3. Meet with UE, or the Missouri Public Service Commission if UE is
unavailable, to obtain pertinent operating and operating cost,
sales, revenue, and proposed capital expenditure data.
4. Prepare preliminary estimate of probable cost of a capital
improvement program for each utility. The estimates will include
supply and interconnection facilities.
5. Determine probable purchase price of the individual utilities.
The price would be based on book value and a market analysis of
earnings value.
6. Estimate the bond issues size and related annual debt service for
each utility necessary to acquire the utility, pay for necessary
capital improvements and pay issuance costs.
7. Determine initial financial feasibility of acquiring each utility
by comparing costs with revenues under existing rates.
8. Evaluate the effects on initial feasibility of utility acquisi-
tion against other alternative acquisition prices, alternative
means of financing capital improvements, and alternative sources
of electric and gas supply, as appropriate.
Alternative sources of electric supply will consider:
- Partial requirements (base load) service from UE and peaking
capacity owned by the City.
- Limited market survey of full and partial requirements power
suppliers in the region.
4
- Transmission facilities required for interconnection of the
acquired system.
Alternative sources of gas supply will consider:
- A limited survey of suppliers in the region.
�
- Transmission service and/or interconnection facilities
required for alternate service suppliers.
9. As an alternative to acquiring the entire electric system, a
study will be made of the feasibility of acquiring the street
lighting system only.
10. Identify sources of revenues to the City which would likely be
affected by the acquisition of one or more of the utilities.
These sources would include: franchise fees, property taxes,
payroll taxes (if applicable), and school taxes.
11. Identify organizational impacts on the City in acquiring and
operating one or more of the utilities. Management and operating
support systems needed to operate the utilities will be identi-
fied.
B. Franchise Agreement Study
The following elements are typical of those which will be evaluated
for inclusion in a renewed franchise agreement.
1. Length of contract and notice of renewal period.
2. Specification of capital improvements to be made to the systems.
3. Assistance from UE with promotion of industrial and community
development.
4. Enhanced coordination of the City' s sewer utility billing with
UE' s water utility billing and customer records.
5. Franchise fee percentages.
C. Presentation
1. Attend two interim meetings with the Citizens Committee to dis-
cuss preliminary findings.
2. Preparation and mailing of 20 copies of preliminary and final
reports or material for inclusion in Citizens Committee report.
3. Presentation of the final report, including findings and recom-
mendations, to a meeting of the City Council.
5
D. Supplemental Services
Any additional work requested by the City that is not included in one of
the items listed in this Appendix A will be classified as supplemental
services.
Supplemental services shall include but are not limited to:
1. Additional meetings with the City Council during their delibera-
tions of the Committee's report as well as meetings with the
public or special boards.
2. Supplemental studies required to meet the requests of the City or
other entities as directed by the City.