HomeMy WebLinkAboutRES.838.07-19-1993 BILL NO. 93-156 RESOLUTION NO. ��t1L�
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
ENTER INTO A CONTRACT AMENDMENT WITH SVERDRUP
CORPORATION FOR ENGINEERING SERVICES FOR THE
WASTEWATER PATHOGEN REDUCTION AND SLUDGE
STORAGE PROJECT
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE GIRARDEAU,
MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the City of
Cape Girardeau, Missouri, is hereby authorized to enter into a
Contract Amendment with Sverdrup Corporation for engineering
services for the wastewater pathogen reduction and sludge storage
project. A copy of said Amendment is attached to this Resolution
and made a part hereof.
v) 1
PASSED AND ADOPTED THIS ��- DAY OF �--� i c.�'�..; , 19 �'�'�
� ��
��x���cx�xx����xx ��
ATTEST: Albert M. Spradling, III , Mayor Pro Tem
�.�1 ` ,,-��
�d fY���.;i.�.!.;� �,�. � J iZ1_c�r.�t`_�
��� �
Kimberly A. Pruett, Deputy City Clerk
AMENDMENT NO. 1
to
AGREEMENT BETWEEN THE
CITY OF CAPE GIRARDEAU, MISSOURI
and
SVERDRUP CORPORATION
Dated February 21, 1992
Note: All other terms of the original contract remain unchanged with the exception of
the following:
Article 3 - Compensation and Payment
On page 3 under A. Cost - Replace the second paragraph with:
The total cost (exclusive of fixed fee) is estimated to be $238,320. The fixed fee
shall be $25,320. The total amount to be paid for design and construction services
- under this Agreement shall not exceed $263,640 including cost and fixed fee,
without approval of the Owner. Sverdrup shall notify the Owner when costs
incuned and obligated amount to 95% of the total estimated cost and shall not
incur costs beyond the estimated cost without prior approval of the Owner. A cost
summary is presented in APPENDIX D.
On page 3 under B. Cost Computation - add to B.1:
The provisional Salary Related Expense overhead rate for Phases II, III - Office,
III - Resident and IV shall be 0.428. At the end of each calendar year, the actual
rate for the year will be applied and adjustment in the compensation made
accordingly. The maximum Salary Related Expense overhead rate that shall be
applied is 0.43.
�rc,r-,is�N.t�vai.sw 1
On page 3, add to B.2:
The General and Administrative overhead rate for Phases II, III - Office and IV
shall be at the office provisional rate of 0.925. The maximum office General and
Administrative overhead rate that shall be applied for Phases II, III - Offices and
N is 0.95.
The Resident Engineer while on assignment in Cape Girardeau is defined as Phase
III - Resident. The General and Administrative overhead factor for Phase III -
Resident shall be at the field provisional rate of 0.43. The maximum field General
and Administrative overhead rate that shall be applied for Phase III - Resident is
0.45.
Article 11 - Contract Documents
On page 9 amend Article 11 to read:
This Agreement consists of:
1. This Document - Agreement for Professional Services
2. APPENDIX A - Scope of Services
3. APPENDIX B - As amended by Amendment 1
4. APPENDIX C - Additional Owner Supplied Information and Activities
5. APPENDIX D - As amended by Amendment 1
6. APPENDIX E - As amended by Amendment 1
Proposed by Sverdrup Corporation:
Date: � � �
�.--
A fred J. Buescher
Vice President
Accepted by City of Cape Girardeau:
By; ATTFST:
J. Ronald Fischer City Clerk
City Manager
Attachments: Amendment 1 to Appendix B
Amendment 1 to Appendix D
Amendment 1 to Appendix E
FY(..'Y•I Ii/AMF1JlY137D 2
Page 1 of 6
AMENDMENT NO. 1
APPENDIX B
Add:
PHASE II - FINAL DESIGN PHASE
SCOPE OF WORK
A. Attend a project initiation meeting in Cape Girardeau, including a visit to the
wastewater treatment plant. Review with the Owner the preliminary design for
the lime treatment system and the sludge holding tank as finalized in the letter to
the Missouri Department of Natural Resources dated 7une 2, 1993. Obtain City
input on design features.
B. Conduct jar tests using calcium hydroxide (CaOH� to determine quantity of
calcium hydroxide (lime) needed to raise the pH of the thickened wastewater
sludge to a pH of 12 for two hours. The Owner will provide representative
sludge. The results will be used in sizing the lime addition equipment.
C. Prepare design calculations to size equipment needed for the lime treatment system
' and sludge holding tank. Sizing will be based on the Facility Plan and the lime
addition testing.
D. Prepare drawings showing the location of the new facilities on the treatment plant
site and providing design information for the construction Contractor. It is
assumed that existing drawings of the wastewater treatment plant site are
sufficiently accurate to use as background and for location of the new structures.
The Owner will provide survey information should it be determined that additional
data is necessary.
E. Prepare design specifications for the equipment and facilities to be added. The
major equipment to be included in the construction documents is:
1. Lime Silo System Including Slurry Tank and Chemical Feed Pumps.
Slaking of calcium oxide is anticipated; however, purchase of calcium
hydroxide will be investigated and used if the Owner concurs with the
feasibility. City water already at the site will be used for mixing the lime
solution.
2. Sludge Contact Tank. This tank is anticipated to be a 25 ft. diameter above
ground bolted steel tank about 10 ft. deep.
Ercra is��t�+�vo-i.3zo
Page 2 of 6
3. Sludge Holding Tank. This tank is anticipated to be an above ground bolteri
steel tank 70 ft. in diameter with about 19 ft. of sludge depth.
4. Sludge Mixers. Both tanks will be mixed. Submersible mixers or jet-type
hydraulic mixers will be considered.
5. Pumps. Centrifugal pumps will be used for sludge transfer, sludge feed and
the sludge holding pumps. Submersible or horizontal pumps will be
considered.
F.. Geotechnical conditions require piling under the lime silo system, sludge contact
tanks and sludge holding tank.
G. Initiation of sludge transfer will be manual with automatic shutoff to prevent
overfilling the tanks. Control and lockout of all the pumps will be from the motor
control center (MCC) located in the sludge building. There will be no local
controls or disconnects.
H. The Owner will provide a transformer to power the MCC. Sverdrup will design
wiring from the transformer to the MCC.
I. Grounding will be into an existing power ground.
J. Prepare bid documents including plans, specifications and contract documents.
Engineers Joint Contract Documents Committee contract documents will be used
or these will be provided by the Owner. Printing of Bid Documents is not part
of this contract.
K. Assist the Owner with submission of plans and specifications to the Missouri
Department of Natural Resources for construction permit application. Prepare
minor revisions as necessary to obtain approval. The Owner will handle obtaining
any local construction permits. No other permits are anticipated.
L. Prepare construction cost estimate based on the construction documents produced.
M. Attend project review meetings with the Owner as follows:
1. Initiation meeting at Cape Girardeau
2. 30% review meeting at Cape Girardeau
3. 90% review meeting at Cape Girardeau