A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE AN ENGINEERING SERVICES CONTRACT WITH
BLATTNER & ASSOCIATES, INC. FOR A FOOTBRIDGE
IN ARENA PARK
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE GIRARDEAU,
MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the City of
Cape Girardeau, Missouri, is hereby authorized to execute an
Engineering Services Contract with Blattner & Associates, Inc. for
a footbridge in Arena Park. A copy of said Contract is attached to
this Resolution and made a part hereof.
PASSED AND ADOPTED THIS ; �`� DAY OF t�'.��1i,Ctu��.��, 19 �,.�
t
Francis E. Rhodes, Mayor
ATTEST:
�;;
c;_r..+��ai r.f�.l,i�,. (.;!' i+ i(i t.%C
G� . Conrad, Deputy City Clerk
�,.
BLATTNER AND ASSOCIATES INC.
PROFESSIONAL ENGINEERING CONSULTANTS
Civil Design • Structural Design • Maferial Testing • Hydrology • Construction Management
City of Cape Girardeau
Arena Parlc Footbridge
January 21 , 1993
ENGINEERING SERVICES CONTRACT
THIS CONTRACT is between the City of Cape Girardeau, Missouri
hereinafter referred to as the "City" , and Blattner & nssociates ,
Inc . , P .O. Box 2137, Cape Girardeau. Missouri 63'1U2 . her,einafter
referred to as the "Engineer" .
INASMi1CH as funds have been made available bY tt�e City of Cape
Girardeau, and inasmuch as the City intends to replace a
Pedestrial Bridge c�ver an existing creek, located in Arena Park,
ar�d therefore reqtzires professional engineering services, the
Engineer will provide the City with prc�fessional services
hereinafter detailed for the planning and design for the
replacement of said structure and t,tle CitY will pay the Engineer
as provided in this Contract . It is mutually agreed as follows :
ARTICLE I - SCOPE OF SERVICES - COMPENSATION
A . PRELIMINARY DESIGN PHASE
The Engineer, for a fee not to exceed $50C� . 00 , shall
prepare a preliminary design report evaluating two
alternatives for final design. The report shall include
a cost estimate for each of the following alternates :
1 . Alternate 1 - A Structural Steel Bridge with Wooden
Ueck, concrete end bents and metal handrail .
2 . Alternate 2 - A refurnished railroad flat car
furnished by others on a concrete foundation and
metal handrail .
B. DE�IGN PHASE
The Engineer 5ha11 prepare detailed cost estimates ,
construction plans , specifications , and bidding
documents for one of the alternates set out in Paragraph
A above .
Compensation shall not exceed 10� of the preliminary
construction cost estimate for the alternate chosen by
PAGE 1
P.O. BOX 2137 • CAPE GIRARDEAU, MO 63702-2137 � (314)339-1139 • (314)339-1129 • FAX; (314) 339-7202
the City (Estimated to be $2500 . 00) .
C. Shop drawing review, and or design modifications as may
be required during construction may be arranged under
Article II following.
ARTICLE II - ADDITIONAL SERVICES
The City reserves the right to request additional work, or
changed or unforeseen conditions may require changes and work
beyond the scope of this Contract . In this event, a supplement
to this agreement shall be executed and submitted for approval
prior to performing the additional or changed work or incurring
any additional cost therefore . Any change in comper�sation will
be covered in the supplemental agreement .
ARTICLE III - RESPONSIBILITIES OF CITY
The City will cooperate fully with the Engineer in the
development of the project , including the following :
A. Make available all information pertainina to the project
which may be in the possession of the City .
B. Provide the Engineer with the City ' s requirements for
the project .
C. Make provisions for the Engineer to enter uFon property
at the project site for the performance of his duties .
D. Examine all studies and layouts developed by the
Engineer , obtain reviews or render decisions thereon, in
a prompt manner, so as not to cause unreasonable delays
to the Engineer .
E. Designate a person in the City ' s employ to act as the
City ' s representative under this Constract . Such person
is to have authority to transmit instructions , interpret
the City ' s policies and render decisions with respect to
matters covered by this agreement .
F. The City will perform appraisals and appraisal review,
negotiate with property owners and otherwise provide all
services in connection with acquiring all right-of-way
needed to construct this pro�ect .
PAGE 2
ARTICLE IV - PERIOD OF SERVICE
The Engineer will commence work within two weeks after receiving
n�tice to proceed from the City and will complete the work within
the times specified and set forth below:
A. Preliminary design phase - thirty days from noticP to
proceed .
B. Final design phasP - Sixty days fram notice of the
alter�native the City wishes to pursue for design.
The abov� times are exclusive of review time by any other
agencies and exclusive of time needed to acquire right-of-way .
The City will grant time extensions for unavoidable delays beyond
the control of the Engineer . Requests for extensions of time
should be requested in writing by the Engineer, stating fully the
reasons for the request .
ARTICLE V - STANDARDS
Design criteria and project planning will be in accordance with
Standar�d Specifications for Highway Bridges as promulgated by the
American Association of Highway and Transportation Officials ,
including sei�;mic considerations . The latest version of Missouri
Standard Specifications for Highway Construction will be used for
Contract Specifications with appropriate modifications thereto by
the Engineer .
ARTICLE VI - ADDITIONAL SERVICES
1 . P .roject costs incurred by others on a subcontract basis .
Said costs are to be passed through the Engineer on the
basis of reasonable and actual cost as invoiced by the
subcontractors .
2 . METHOD OF PAYMENT - Partial Payments for work
satisfactorilY completed will be made to the Engineer
upon receipt of itemized invoices by the City . Invoices
will be submitted no more frequently the one invoice per
' month .
3 . The Engineer shall furnish the City a Certificate of
Insurance, valid throughout the term of this Contract,
for general liability of $1 , 000, 000 and $100, 000 per any
PAGE 3
accident. and shall provide the City with a Certificate
of Workmen ' s Compensation Insurance .
ARTICLE VII - PROFESSIONAL ENDORSE�iENT
All plans , specifications and other documents shall be endorsed
bY the Engineer and shall reflect the name and seal of the
Professional Engineer endorsing the work.
ARTICLE VIII — RETENTION OF RECORDS
The Engineer shall maintain all records , survey notes, design
documents , cost and accounting records, construction records and
other records pertaining to this Contract and to the project
covered bY this Contract , for a period of not less than three
years following final payment by the City. Said records shall be
made available for inspection by authorized representatives of
the CitY or the Federal Government during regular working hours
at the Engineer ' s place of business .
ARTICLE IX — OWNERSHIP OF DOCUMENTS
Plans, tracings, maps and specifications prepared under this
Contract shall be made available to the City upon request . All
such information produced under this Contract shall be available
for use by the City without restriction of limitation of its use .
If the City inc�rporates anY Portion of the work into a project
other than that for which it was performed, the City shall save
� the Engineer harmless from any claims and liabilities resulting
from such use .
ARTICLE X — TERMINATION
The City maY terminate the Contract at any time by giving written
notice . If the Contract is terminated because the project is
abandoned or postponed by the City, the Engineer will be Faid for
actual expense incurred up to the date of termination.
If the Contract is terminated due to the Engineer ' s services
being unsatisfactory in the judgement of the City, or if the
Engineer fails to prosecute the work with due diligence , the City
may pro�ure completion of the work in such a manner as it deems
to be in the best interest of the City . The Engineer will be
responsible for any excess cost in addition to that provided for
in thi� Contract or anY damages the City maY sustain by reason of
. PAGE 4
the termination of this Contract due to unsatisfactory
performances or prosecution .
ARTICLE XI — COMPLIANCE WITH LAWS
The Engineer shall comply with all Federal , State , and Local
Laws , Ordinances , and Regulations applicable to the work,
including Title VI of the Civil Rights Act of 1964 and non—
discrimination clauses incorporated herein as Attachment C and
shall procure all licenses and permits necessary for the
fulfillment of obligations under this Contract .
ARTICLE XII — RESPONSIBILITY FOR CLAIMS AND LIABILITY
, The Engineer agrees to save harmless, the City from all claims
and liabilities due to his negligent acts or the negligent acts
of his employees , agents or subcontractors .
ARTICLE XIII — NONDISCRIMINATION
The Engineer, with regard to the work performed by it after award
and prior to completion af the Contract work, will not
discriminate on the grounds of race, color or national origin in
the selection and. retention of subcontractors . The Engineer will
comply with Title VI of the Civil Rights Act of 1964, as amended .
ARTICLE XIV
This Contract is made and entered into subject to the approval of
the City Council of Cape Girardeau.
PAGE 5
Executed by the Engineer on this � day of� , 1993 .
Executed by the City This 1� day of ��, 1993 .
FOR: CAPE GIRARDEAU CITY,
c
BY: �
J ONALD FISC ER, CITY MANAGER
ATTEST:
. , Deputy City Clerk
�lG. L - �' n r'a c�.
BY: BLATTNER & ASSOCIATES, INC .
BY : L.�'�i� '�---
CHARLES F . BLATTNER III , PRESIDENT
AT"I'ES - -�__ Q , � d��
�. ` - TRACY D BLATTNER, SECRETARY
`_• " —
PAGE 6