HomeMy WebLinkAboutRES.1658.04-02-2001BILL NO. 2001-72
RESOLUTION NO. 5
A RESOLUTION AUTHORIZING THE CITY
MANAGER TO EXECUTE AN ADDENDUM TO
THE RODNEY STREET DESIGN ADDENDUM
TO THE GENERAL SERVICES CONTRACT
DATED OCTOBER 5, 1998, WITH BOWEN
ENGINEERING AND SURVEYING
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE GIRARDEAU,
MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the City
of Cape Girardeau, Missouri, us hereby authorized to execute an
Addendum to the Rodney Street Design Addendum to the General
Services Contract dated October , 1998, with Bowen Engineering
and Surveying. A copy of said Addendum is attached to this
Resolution and made a part hereof.
PASSED AND ADOPTED THIS DAY OF , 20 1-)(.
, 6�� V -
A. M. Spradling, III, ayor
ATTEST:
Gayler . Conrad, City Clerk,�615K �'
h?}
November 27, 2000
City of Cape Girardeau
Office of the City Engineer
401 Independence Street
Cape Girardeau, MO 63701
Attn.: Mark Lester
RE: Rodney Street Design
Dear Mr. Lester:
We have completed the design of Rodney Street, and to our knowledge the project is
ready for advertising and construction with the exception of date insertions into the
specifications. The basic design contract amount was for $ 61,000.00. The engineering
work for the basic scope of services was completed and submitted to the City about
May 2000.
As a result of your review and negotiations with adjacent landowners, a change to the
basic scope of work was necessary, and these changes were set forth in your May 30,
2000 correspondence. These changes required a major change in the design of the
bridge and the entrance to the adjacent Car Wash. The cost of this redesign was
$ 19, 510.00.
Also, the limits of the project were increased by about 600 linear feet along Rodney
Street to the beginning of the existing concrete pavement near the intersection of West
Rodney Drive. This extension required the design of two intersections. This work was
completed and the cost was $ 9,985.00.
Also, for the completion of this project, test borings were necessary. Two test boring
holes were drilled at approximately each end of the proposed bridge. This work was
completed and the cost was $ 1,874.16.
Our invoice for basic contractual services and the invoices for the additional work are
attached.
Consulting Civil Engineers Land Surveyors Testing Laboratories
Wolverine Lane, Suite J
Cape Girardeau, 61
w1078
Boen
Ph 573 338 5900 3 139
Fax 573 339 1391
email - bowenengaldd.net
ENGINEERING &
SURVEYING
Incorporated
November 27, 2000
City of Cape Girardeau
Office of the City Engineer
401 Independence Street
Cape Girardeau, MO 63701
Attn.: Mark Lester
RE: Rodney Street Design
Dear Mr. Lester:
We have completed the design of Rodney Street, and to our knowledge the project is
ready for advertising and construction with the exception of date insertions into the
specifications. The basic design contract amount was for $ 61,000.00. The engineering
work for the basic scope of services was completed and submitted to the City about
May 2000.
As a result of your review and negotiations with adjacent landowners, a change to the
basic scope of work was necessary, and these changes were set forth in your May 30,
2000 correspondence. These changes required a major change in the design of the
bridge and the entrance to the adjacent Car Wash. The cost of this redesign was
$ 19, 510.00.
Also, the limits of the project were increased by about 600 linear feet along Rodney
Street to the beginning of the existing concrete pavement near the intersection of West
Rodney Drive. This extension required the design of two intersections. This work was
completed and the cost was $ 9,985.00.
Also, for the completion of this project, test borings were necessary. Two test boring
holes were drilled at approximately each end of the proposed bridge. This work was
completed and the cost was $ 1,874.16.
Our invoice for basic contractual services and the invoices for the additional work are
attached.
Consulting Civil Engineers Land Surveyors Testing Laboratories
Please sign a copy of this letter which will serve as our authorization for the extra work.
If there are any questions, or if additional information is required, please do not hesitate
to call.
Sincerely,
a
Cary Harbison
FOR: Bowen Engineering & Surveying, Inc.
i� �►
i 'W • 1. Bowen,
FOR: City/b/fCape Girardeau
TE: Y—,5 'd %
CITY MAPAa
Consulting Civil Engineers Land Surveyors Testing Laboratories
CHANGE ORDER #1
PROJECT TITLE: Rodney Street (Cape Lacroix Creek And Pavement Reconstruction)
CONTRACT DATE: June 6, 2001
CONTRACTOR: Bowen Engineering & Surveying, Inc.
The following changes are hereby made to the Amendment to the General Services
Contract Documents:
Part 1: Additional Quantities
NO Item Unit Additional Contract Price
Quantity Unit Price
1 3 -man survey crew HR 24 $ 70.00 $ 1680.00
2 Additional Mileage Mile 90 $ 0.30 $ 27.00
TOTAL $ 1707.00
Justification
Additional staking was required for the bridge bents in the creek, caused by unanticipated
foundation conditions and a change in the design of the bridge center supports.
Change to Contract Price
Original contract price:
$ 7,195.00
Current contract price due to this change order will be increased by:
$ 1,707.00
The new contract price due to this change order will be:
$ 8,902.00
Change to Contract Time
No change due to this change order.
Approval Required:
To be effective, this Change Order must be approved by the owner if it changes the scope
or objective of the project, or may otherwise be required under the terms of the Supplementary
General Conditions to the Contract.
Recommended by `Iry Date p 2 /ULI/0 2_
Abdulkader Alkadry, Project Manager
Approved by
Date G
;Z- c24 _ o
Michaels Miller, City Manager
Accepted by 414Date Z Z /I 6 Z