HomeMy WebLinkAboutRES.1639.01-22-2001BILL NO. 2001-13
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY
MANAGER TO EXECUTE AGREEMENT WITH
CRAWFORD, MURPHY & TILLY, INC., FOR
DESIGN AND CONSTRUCTION OVERSIGHT
SERVICES FOR THE INSTALLATION OF A
STANDBY GENERATOR AND OTHER
ELECTRICAL IMPROVEMENTS AT THE CAPE
GIRARDEAU REGIONAL AIRPORT
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE GIRARDEAU,
MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the City
of Cape Girardeau, Missouri, is hereby authorized to execute an
Agreement with Crawford, Murphy & Tilly, Inc., for design and
construction oversight services for the installation of a standby
generator and associated vault electrical service modifications,
Project No. A.I.P. 3-29-0013-09, at the Cape Girardeau Regional
Airport. A copy of said Agreement is attached to this Resolution
and made a part hereof.
PASSED AND ADOPTED THIS DAY OF , 20
A. Spradling, III, May
ATTEST:,
Gayle L. Conrad, City Clerk
CAPE GIRARDEAU REGIONAL AIRPORT
STANDBY GENERATOR INSTALLATION AND ASSOCIATED
VAULT ELECTRICAL SERVICE MODIFICATIONS
AIRPORT PROJECT NO. A.I.P. 3-29-0013-09
THIS PROJECT AGREEMENT NUMBER Z which amends the Professional Services
Contract dated August 18, 1998, made and entered into this Z3,tct day of J-0 nuav q, fool by and
between the CITY OF CAPE GIRARDEAU, MISSOURI, whose address is 401 Independence
Street, Cape Girardeau, Missouri, 63702, a municipal corporation, acting by and through its City
Council, hereinafter referred to as "SPONSOR" and CRAWFORD, MURPHY & TILLY, INC.
Consulting Engineers, whose address is Gateway Tower, One Memorial Drive, Suite 500, St. Louis,
Missouri, 63102, hereinafter referred to as "CONSULTANT".
WHEREAS, the Sponsor requires professional services of the Consultant to provide necessary
engineering and related services for design and construction of the following project at the Cape
Girardeau Regional Airport:
Standby Generator Installation and Associated Vault Electrical Service Modifications
Project No. A.I.P. 3-29-0013-09
and WHEREAS, the Consultant has agreed to provide the professional services required which shall
include architectural, civil, structural, mechanical, and electrical engineering services.
NOW, THEREFORE, in consideration of the covenants and agreement hereinafter set forth, it is
agreed as follows:
ARTICLE 1. SCOPE OF SERVICES
1.1 General. The Consultant, in consideration of the payment on the part of the Sponsor, agrees
to perform the engineering services in accordance with Article II of the Professional Services
Contract as modified by the remainder of this Article 1.
DESCRIPTION OF PROJECT: This project consists of the installation of a standby generator along
with the additional vault modifications required to allow for the new generator.
The Consultant is to prepare construction plans, contract documents, and technical specifications
necessary for competitively bidding the work required for the installation of the standby generator.
The Consultant shall provide construction phase services during the construction of the project. The
Consultant will not be required to have a full-time representative on the site during construction of
Page 1 of 4
00405-01-00 9/2000
the improvements. The Sponsor's personnel will provide the daily on-site construction observation.
The Consultant will provide a site representative only on an as needed basis.
1.2 Basic Design Services Phase. This phase of the project shall include the engineering services
listed in Article II, Part B - Basic Design Services of the Professional Services Contract. The
specific tasks to be accomplished and the level of effort intended and estimated for each task for this
phase are listed on Attachment "A" under the heading for Basic Design Services.
1.3 Construction Phase Services. This phase of the project shall include the engineering services
listed in Article II, Part C - Construction Phase Services of the Professional Services Contract. The
specific tasks to be accomplished and the level of effort intended and estimated for each task for this
phase are listed on Attachment "B" under the heading for Construction Phase Services.
ARTICLE 2. SCHEDULE
The Consultant agrees to submit preliminary plans, specifications, contract documents, and
opinion of probable construction cost not more than 90 days after written Notice to Proceed. The
Consultant agrees to have final plans, specifications, and contract documents ready fbr advertising
for construction bids not more than 30 days after written review comments on the preliminary plans,
specifications, and contract documents are received from the Sponsor and the Missouri Highway and
Transportation Department, Aviation Section.
ARTICLE 3. COMPENSATION
3.1 Compensation for services outlined in Article 1, Paragraph 1.2 of this Project Agreement,
Basic Design Phase Services, shall be a lump sum fee basis with the fee being $18,400 without a
modification to this Project Agreement. The estimated costs for the Consultants' Services for this
part of the work is shown as "Attachment A". For the work under this paragraph the Consultant shall
submit monthly statements to the Sponsor showing the percentage of the work completed. If a
decision is made not to advertise the projects for bids, for whatever reason, any remaining portion of
the fee for this phase of the project shall be included on the next statement from the Consultant.
3.2 Compensation for services outlined in Article 1, Paragraph 1.3 of this Project Agreement,
Construction Phase Services, shall be on a cost plus fixed fee basis with the fixed fee being $750 and
the total amount not to exceed $5,700 without a modification to this Project Agreement. The
estimated costs for the Consultants' Services for this part of the work is shown as "Attachment B".
For the work under this paragraph the Consultant shall submit monthly statements to the Sponsor for
all payroll costs and all other expenses incurred on the project and shall include a pro -rata share of
the fixed fee in proportion of the statement amount to the not to exceed amount. Upon final
completion and acceptance of the project any remaining portion of the fixed fee shall be included on
the final statement from the Consultant.
Page 2 of 4
00405-01-00 9/2000
3.3 Payments shall be made to the Consultant by the Sponsor within sixty (60) days of receipt of
proper billing. Invoices which are not paid within sixty (60) days of receipt of proper billing shall
bear interest at the rate of 1-1/2% for each month or fraction thereof from the date sixty (60) days
after receipt of proper billing to time of payment.
Page 3 of 4
00405-01-00 9/2000
IN WITNESS WHEREOF, the parties hereto affixed their signatures this
6?3rd day of ; r(_ , 20 C1 .
SPONSOR
CITY OF CAPE GIRARDEAU, MISSOURI
acting through -its City Council.
ATTEST:
ATT
CONSULTANT
Crawford, Murphy & Tilly, Inc.
Page 4 of 4
00405-01-00 9/2000
ATTACHMENT A - PAGE 1 OF 1
ESTIMATED COST FOR CONSULTANTS' SERVICES (BASIC DESIGN SERVICES)
CAPE GIRARDEAU REGIONAL AIRPORT
STANDBY GENERATOR INSTALLATION AND ASSOCIATED
VAULT ELECTRICAL SERVICE MODIFICATIONS
AIRPORT PROJECT NO. A.I.P. 3-29-0013-09
BASIC DESIGN SERVICES
1. Direct Salary Costs
Title Hours
Rate/Hour
Cost $
Principal of Firm
0
$55.36
$ 0.00
Sr. Project Engineer
12
37.62
451.44
Project Engineer
120
29.26
3511.20
Senior Engineer
0
24.18
0.00
Engineer
0
20.10
0.00
Senior Eng. Tech.
95
21.23
2016.85
Engineering Tech.
0
16.31
0.00
Clerical
0
12.78
0.00
Total Direct Salary Costs $5979.49
2. Labor and General & Administrative Overhead
Percentage of Direct Salary Costs 154.80% $ 9256.25
3. Direct Nonsalary Expenses
Transportation & Lodging $ 300.00
Printing 450.00
Supplies & Misc. 50.00
Total Direct Nonsalary Expenses$ 800.00
4. Subtotal of Items 1, 2 and 3 $ 16,035.74
5. Profit (approximately 15% of Item 4) $ 2,405.36
6. Subcontract costs (specify)
Total Subcontract Costs $ 0.00
Items 4, 5, plus 6 $ 18,441..1
Therefore use $18,400 for a lump sum fee.
00405-01-00 9/2000
y ATTACHMENT B - PAGE 1 OF 1
ESTIMATED COST FOR CONSULTANTS' SERVICES (CONSTRUCTION SERVICES PHASE)
CAPE GIRARDEAU REGIONAL AIRPORT
STANDBY GENERATOR INSTALLATION AND ASSOCIATED
VAULT ELECTRICAL SERVICE MODIFICATIONS
AIRPORT PROJECT NO. A.I.P. 3-29-0013-09
CONSTRUCTION PHASE SERVICES
1. Direct Salary Costs
Title Hours
Rate/Hour Cost $
Principal of Firm
0
$55.36
$ 0.00
Sr. Project Engineer
0
37.62
0.00
Project Engineer
60
29.26
1755.60
Senior Engineer
0
24.18
0.00
Engineer
0
20.10
0.00
Senior Eng. Tech.
0
21.23
0.00
Engineering Tech.
0
16.31
0.00
Clerical
5
12.78
63.90
Total Direct Salary Costs $ 1819.50
2. Labor and General & Administrative Overhead
Percentage of Direct Salary Costs 154.80% $ 2816.59
3. Direct Nonsalary Expenses
Transportation & Lodging $ 300.00
Printing 0.00
Supplies & Misc. 50.00
4. Subtotal of Items 1, 2 and 3
Total Direct Nonsalary Expenses$ 350.00
$ 4986.09
5. Fixed Payment (approximately 15% of Item 4) $ 750.00
6. Subcontract costs (specify)
Total Subcontract Costs $ 0.00
Total Cost
Items 4, 5, plus 6 $ 5736.09
Therefore use $5,700 for a cost plus fixed fee contract upper limit.
00405-01-00 9/2000