HomeMy WebLinkAboutRES.1579.07-03-2000BILL NO. 2000-165
RESOLUTION NO. / J -] `�
A RESOLUTION AUTHORIZING THE CITY
MANAGER TO EXECUTE AN AGREEMENT
WITH FRONABARGER CONCRETERS, INC.
FOR THE HOPPER ROAD EXTENSION,
PHASE I
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE GIRARDEAU,
MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the City
of Cape Girardeau, Missouri, is hereby authorized to execute an
Agreement with Fronabarger Concreters, Inc., for the Hopper Road
Extension, Phase I. A copy of said Agreement is attached to this
Resolution and made a part hereof.
PASSED AND ADOPTED THIS ' DAY OF Lle ki 20"
e
4'4�� WZ7W,
A. M. Spradling, III,&Y—or
ATTEST:
�L)o 0� 6
Gayle L Conrad, City Clerk
CITY OF CAPE GIRARDEAU
HOPPER ROAD EXTENSION
PHASE
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
ON THE BASIS OF A STIPULATED PRICE
THIS AGREEMENT is dated as of the day of in the year
20_ by and between the City of Cape Girardeau, Missouri (hereinafter called OWNER)
and Fronabarger Concreters, Inc. (hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set
forth, agree as follows:
Article 1. WORK.
CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents. The Work is generally described as follows:
The work to be performed under these Contract Documents shall consist of
of all necessary grading, excavation and embankment construction, storm
sewers, drainage structures, construction of a seven-inch concrete pavement
with concrete curb and other related construction items necessary to
accomplish the work in accordance with the Plans and as stated in the
Specifications prepared by Bowen Engineering & Surveying, Inc. dated May,
2000.
This work is for the City of Cape Girardeau, Missouri.
Article 2. ENGINEER.
The City Engineer or his designee is to act as OWNER's representative, assume all duties
and responsibilities and have the rights and authority assigned to "ENGINEER" in the
Contract Documents in connection with completion of the Work in accordance with the
Contract Documents.
A-1
Article 3. CONTRACT TIMES.
3.1 The work will be substantially completed within one -hundred eighty (180) calendar
days after the date when the Contract Times commence to run as provided in paragraph
2.3 of the General Conditions, and competed and ready for final payment in accordance
with paragraph 14.13 of the General Conditions within two -hundred ten (210) days after the
date when the Contract Times commence to run.
3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the
essence of this Agreement and that OWNER will suffer financial loss if the Work is not
completed within the times specified in paragraph 3.1 above, plus any extensions thereof
allowed in accordance with Article 12 of the General Conditions. They also recognize the
delays, expense and difficulties involved in proving the actual loss suffered by OWNER if
the Work is not completed on time. Accordingly, instead of requiring any such proof,
OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a
penalty) CONTRACTOR shall pay OWNER Three -Hundred Dollars 300.00 for each
day that expires after the time specified in paragraph 3.1 for Substantial Completion until
the Work is substantially complete. After Substantial Completion, if CONTRACTOR shall
neglect, refuse or fail to complete the remaining Work within the time specified in paragraph
3.1 for completion and readiness for final payment or any proper extension thereof granted
by OWNER, CONTRACTOR shall pay OWNER Three -Hundred Fifty Dollars ($ 350.00)
for each day that expires after the time specified in paragraph 3.1 for completion and
readiness for final payment.
Article 4. CONTRACT PRICE.
OWNER shall pay CONTRACTOR for completion of the Work in accordance with the
Contract Documents an amount in current funds equal to the sum of the amounts
determined pursuant to paragraph 4.2 below:
4.2 for all Unit Price Work, an amount equal to the sum of the established unit price for
each separately identified item of Unit Price Work times the estimated quantity of that item
as indicated in the bidding documents.
TOTAL OF ALL UNIT PRICES: Five hundred fifty-two thousand, six hundred seventy
nine dollars and ninety-six cents($ 552.679.96
As provided in paragraph 11.9 of the General Conditions estimated quantities are not
guaranteed, and determinations of actual quantities and classification are to be made by
ENGINEER as provided in paragraph 9.10 of the General Conditions. Unit prices have
been computed as provided in paragraph 11.9.2 of the General Conditions.
A-2
Article 5. PAYMENT PROCEDURES.
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER as
provided in the General Conditions.
5.1 Progress payments; Retainage. OWNER shall make progress payments on account
of the Contract Price on the basis of CONTRACTOR's Application for Payment as
recommended by ENGINEER, on or about the 10th day of each month during construction
as provided in paragraphs 5.1.1 and 5.1.2 below. All such payments will be measured by
the schedule of values established in paragraph 2.9 of the General Conditions (and in the
case of Unit Price Work based on the number of units completed) or, in the event there is
no schedule of values, as provided in the General Requirements.
5.1.1 Prior to Substantial Completion, progress payments will be made in an amount equal
to the percentage indicated below, but, in each case, less the aggregate of payments
previously made and less such amounts as ENGINEER shall determine, or OWNER may
withhold, in accordance with paragraph 14.7 of the General Conditions.
90% of Work completed (with the balance being retainage). If Work has
been 50% completed as determined by ENGINEER, and if the character and
progress of the Work have been satisfactory to OWNER and ENGINEER,
OWNER, on recommendation of ENGINEER, may determine that as long as
the character and progress of the Work remain satisfactory to them, there will
be no additional retainage on account of Work completed, in which case, the
remaining progress payments prior to Substantial Completion will be an
amount equal to 100% of the Work completed.
90% (with the balance being retainage) of materials and equipment not
incorporated in the Work (but delivered, suitably stored and accompanied by
documentations satisfactory to OWNER as provided in paragraph 14.2 of the
General Conditions).
5.1.2 Upon Substantial Completion, in an amount sufficient to increase total payments to
CONTRACTOR to 95% of the Contract Price (with the balance being retainage), less such
amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with
paragraph 14.7 of the General Conditions.
5.2 Fina/ Payment. Upon final completion and acceptance of the Work in accordance with
paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the
Contract Price as recommended by ENGINEER as provided in said paragraph 14.13.
A-3
Article 6. INTEREST.
All moneys not paid when due as provided in Article 14 of the General Conditions shall bear
interest at the maximum rate allowed by law at the place of the Project.
Article 7. CONTRACTOR'S REPRESENTATIONS.
In order to induce OWNER to enter into the Agreement, CONTRACTOR makes the
following representations:
7.1 CONTRACTOR has examined and carefully studied the Contract Documents
(including the Addenda listed in paragraph 8) and the other related data identified in the
Bidding Documents, including "technical data".
7.2 CONTRACTOR has visited the site and become familiar with and is satisfied as to the
general, local and site conditions that may affect cost, progress, performance and
furnishing of the Work.
7.3 CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws
and Regulations that may affect cost, progress, performance and furnishing of the Work.
7.4 CONTRACTOR acknowledges that OWNER and ENGINEER do not assume
responsibility for the accuracy or completeness of information and data shown or indicated
in the Contract Documents with respect to Underground Facilities at or contiguous to the
site. CONTRACTOR has obtained and carefully studied (or assumes responsibility for
having done so) all such additional supplementary examinations, investigations,
explorations, tests, studies and data concerning conditions (surface, subsurface and
Underground Facilities) at or contiguous to the site or otherwise which may affect cost,
progress, performance or furnishing of the Work or which relate to any aspect of the
means, methods, techniques, sequences and procedures of construction to be employed
by CONTRACTOR and safety precautions and programs incident thereto. CONTRACTOR
does not consider that any additional examinations, investigations, explorations, tests,
studies or data are necessary for the performance and furnishing of the Work at the
Contract Price, within the Contract Times and in accordance with the other terms and
conditions of the Contract Documents.
7.5 CONTRACTOR is aware of the general nature of work to be performed by OWNER
and others at the site that relates to the Work as indicated in the Contract Documents.
7.6 CONTRACTOR has correlated the information known to CONTRACTOR, information
and observation obtained from visits to the site, reports and drawings identified in the
Contract documents and all additional examinations, investigations, explorations, tests,
studies and data with the Contract Documents.
7.7 CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities
or discrepancies that CONTRACTOR has discovered in the Contract Documents and the
F&MI
written resolution thereof by ENGINEER is acceptable to CONTRACTOR, and the Contract
Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.
Article 8. CONTRACT DOCUMENTS.
The Contract Documents which comprise the entire agreement between OWNER and
CONTRACTOR concerning the Work consist of the following:
8.1 This Agreement (pages 1 to 7 inclusive).
8.2 Exhibits to this Agreement (pages _ to _, inclusive).
8.3 Performance, Payment, and other Bonds, identified as exhibits _ and consisting
of _ pages.
8.4 Notice to Proceed.
8.5 General Conditions (pages 1 to 55 , inclusive, Available upon request).
8.6 Supplementary Conditions (pages SC -1 to SC -5, inclusive).
8.7 Specifications bearing the title HOPPER ROAD EXTENSION PHASE I.
8.8 Standard Specifications for Street Improvements and Sidewalk Improvements
(Available upon request).
8.9 Drawings.
8.10 Addenda numbers 1 to _, inclusive.
8.11 CONTRACTOR's Bid (pages BF -1 to BF -8 , inclusive) marked exhibit A .
8.12 Documentation submitted by CONTRACTOR prior to Notice of Award (pages to
_, inclusive).
8.13 The following which may be delivered or issued after the Effective Date of the
Agreement and are not attached hereto: All Written Amendments and other documents
amending, modifying or supplementing the Contract Documents pursuant to paragraphs
3.5 and 3.6 of the General Conditions.
The documents listed in paragraphs 8.2 et seq. above are attached to this Agreement
(except as expressly noted otherwise above).
A-5
There are no Contract Documents other than those listed above in the Article 8. The
Contract Documents may only be amended, modified or supplemented as provided in
paragraphs 3.5 and 3.6 of the General Conditions.
Article 9. MISCELLANEOUS.
9.1 Terms used in this Agreement which are defined in Article 1 of the General Conditions
will have the meanings indicated in the General Conditions.
9.2 No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of the party
sought to be bound; and, specifically but without limitation, moneys that may become due
and moneys that are due may not be assigned without such consent (except to the extent
that the effect of this restriction may be limited by law), and unless specifically stated to the
contrary in any written consent to an assignment no assignment will release or discharge
the assignor from any duty or responsibility under the Contract Documents.
9.3 OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and
legal representatives to the other party hereto, its partners, successors, assigns and legal
representatives in respect to all covenants, agreements and obligations contained in the
Contract Documents.
9.4 Any provision or part of the Contract Documents held to be void or unenforceable
under any Law or Regulation shall be deemed stricken, and all remaining provisions shall
continue to be valid and binding upon OWNER and CONTRACTOR, who agree that the
Contract Documents shall be reformed to replace such stricken provision or part thereof
with a valid and enforceable provision that comes as close as possible to expressing the
intention of the stricken provision.
A-6
� �
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed the Agreement in
muitiple copies, One counterpart each has been delivered to CONTRACTOR and
ENGINEER and two counterparts to the OWNER. All portions of the Contract Documents
have been signed, initialed or identified by OWNER and CONTRACTOR or identified by
ENGINEER on their behalf.
This Agreement will be effective on , 20�(which is the Effective Date of
the,.l�kgteeme t).
OWNER �t of Ca e Girardeau CONTRACTOR Fronabarger Concreters, .Ir}c.
Micha � . Mi Cit Mana er � --
z g •
� B
y: - _
�' [CORPO EAL] [ R ORATE S L] � � _
,/'� � __
, ,
Attest Attest
Address for ving notices Addre s for giving notices
401 Independence Street 3290 State Hiqhway E
Cape Girardeau. MO 63702 Oak Ridge, MO 63769
(If OWNER is a public body, attach License No.
evidence of authority to sign and
resolution or other documents Agent for service of process:
authorizing execution of Agreement.
(If CONTRACTOR is corporation, attach
evidence of authority to sign.)
A-7
EXHIBIT A
CITY OF CAPE GIRARDEAU
HOPPER ROAD EXTENSION
PHASE
BID FORM
(EJCDC 1910-18) (1990)
PROJECT IDENTIFICATION: The work to be performed under these Contract
Documents consists of all necessary grading, excavation and embankment construction,
storm sewers, drainage structures, construction of a seven-inch concrete pavement with
concrete curb and other related construction items necessary to accomplish the work in
accordance with the Plans, and as stated in the Specifications and Contract Documents
for this Project. The work is for the City of Cape Girardeau, Missouri.
THIS BID IS SUBMITTED TO:
CITY OF CAPE GIRARDEAU, MO
401 INDEPENDENCE STREET
CAPE GIRARDEAU, MO X3702-0617
1. The undersigned BIDDER proposes and agrees, if the Bid is accepted, to enter into an
agreement with OWNER in the form included in the Contract Documents to perform and
furnish all Work as specified or indicated in the Contract Documents for the Bid Price and
within the Bid Times indicated in this Bid and in accordance with the other terms and
conditions of the Contract Documents.
2. BIDDER accepts all of the terms and conditions of the Advertisement or Invitation to Bid
and Instructions to Bidders, including without limitation those dealing with the disposition
of Bid security. This Bid will remain subject to acceptance for thirty-five days after the day
of Bid opening. THE BIDDER will sign and deliver the required number of counterparts of
the Agreement with the Bonds and other documents required by the Bidding Requirements
within fifteen days after the date of OWNER'S notice of Award.
3. In submitting this Bid, BIDDER represents, as more fully set forth in the Agreement, that:
(a) BIDDER has examined and carefully studied the Bidding Documents and the
following Addenda, receipt of all which is hereby acknowledged: (List Addenda by
Addendum Number and Date)
MDD.6N Dom
BF -1
(b) BIDDER has visited the site and become familiar with and is satisfied as to the general,
local and site conditions that may affect cost, progress, performance and furnishing of the
Work;
(c) BIDDER is familiar with and is satisfied as to all federal, state and local Laws and
Regulations that may affect cost, progress, performance and furnishing of the Work.
(d) BIDDER acknowledges that OWNER and Engineer do not assume responsibility for
accuracy or completeness of information and data shown or indicated in the Bidding
Documents with respect to Underground Facilities at or contiguous to the site. BIDDER
has obtained and carefully studied (or assumes responsibility for having done so) all such
additional or supplementary examinations, investigations, explorations, tests, studies and
data concerning conditions (surface, subsurface and Underground Facilities) at or
contiguous to the site or otherwise which may affect cost progress, performance or
furnishing of the Work or which relate to any aspect of the means, methods, techniques,
sequences and procedures of construction to be employed by BIDDER and safety
precautions and programs incident thereto. BIDDER does not consider that any additional
examinations, investigations, explorations, tests, studies or data are necessary for the
determination of this Bid for performance and furnishing of the Work in accordance with the
times, price and other terms and conditions of the Contract Documents.
(e) BIDDER is aware of the general nature of Work to be performed by Owner and
others at the site that relates to Work for which this Bid is submitted as indicated in the
Contract Documents.
(f) BIDDER has correlated the information known to BIDDER, information and
observations obtained from visits to the site, reports and drawings identified in the Contract
Documents and all additional examinations, investigations, explorations, tests, studies and
data with the Contract Documents.
(g) BIDDER has given Engineer written notice of all conflicts, errors, ambiguities or
discrepancies that BIDDER has discovered in the Contract Documents and the written
resolution thereof by ENGINEER is acceptable to BIDDER, and the Contract Documents
are generally sufficient to indicate and convey understanding of all terms and conditions
for performing and furnishing the Work for which this Bid is submitted.
(h) This Bid is genuine and not made in the interest of or on behalf of any undisclosed
person, firm or corporation and is not submitted in conformity with any agreement or rules
of any group association, organization or corporation; BIDDER has not directly or indirectly
induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not
solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER
has not sought by collusion to obtain for itself any advantage over any other Bidder or over
OWNER.
(i) (Any other representation required by Laws and Regulations.)
BF -2
4. BIDDER will complete the Work in accordance with the Contract Documents for the
following price(s):
BF -3
Unit Price Bid
Hopper Road Extension, Phase I
Cape Girardeau Missouri
NO
BF-4
ITEM
UNIT
EST.
QTY
UNIT
PRICE
ESTIMATED
AMOUNT
1
REMOVE EXISTING IMPROVEMENTS
L.S.
1
11, DO 0.00
/l, 000, 00
2
CLEARING & GRUBBING
ACRES
3.32
3
CLASS "B" EXCAVATION
CU. YD
51,144
4
"
a Z
—
—
5
SPOIL
CU. YD
16,676
a,S'p
yfl, 6 90, 00
6
7" P.C. CONCRETE PAVEMENT
SQ. YD
14,381
g . Ov
A7.3.2 3 9-66
7
4" TYPE "V" AGGREGATE BASE
-YD
15,174.
1 6^0
19 76 1.610
8
6" GRADE "B" SURFACE AGGREGATE
Q. YD
94
/. co
/yl/.OD
9
2" BITUMINOUS PAVEMENT, BP -1
TON
8
S0. 00
404.60
10
5" BITUMINOUS BASE MATERIAL
TON
21
.5-0.00
/DSO.OD
11
PRIME COAT
GAL.
74
00
a�,'(, DD
12
4" P.C. CONCRETE SIDEWALK
SQ. YD
1,541
D, DO
3D 40.
13
4' DIA. JUNCTION MANHOLE
EACH
2
J , 00.00
Al 1100.4,0
14
3'-6"X T -O" SINGLE CURB INLET
EACH
11
1 900.00
J9, 900.00
15
4'-0" X 4'-0" SINGLE CURB INLET
EACH
2
1 b00.00
a 000.00
16
5'-0" X 4'-0" SINGLE CURB INLET
EACH
1
1 �JOD. QQ
/1466 •QQ
17
3'-0" X T-0" GRATED INLET
EACH
1
0D
.2-f . DO
18
15" R.C.P.
L.F.
159
/7.40
744-640
19
18" R.C.P.
L.F.
491
I�.Gg
9 17/•89
20
18" F.E.S.
EACH
6
DD
1'.5-40,06
21
REMOVE AND RELAY EXISTING 18"
F.E.S.
24" R.C.P.
24" F.E.S.
EACH
1
JOD.00
/00, 00
22
L.F.
680.5
JS'.7S
17S 88
23
EACH
2
3 a.00
/' 6 D, DO
24
30" R.C.P.
L.F.
136.5
, O
OQ
25
30" F.E.S.
RIP RAP IN PLACE (18" THICK)
EACH
2
26
SQ. YD
244
0.60
2,41410.00
27
FERTILIZER, SEEDING, & MULCHING
ACRES
5 5
J OD
IoOD.DO
28
EROSION CONTROL
L.S.
1
7 Dgrj.DO
7,0A0-
DDD•
BF-4
NO
ITEM
UNIT
EST.
QTY
UNIT
PRICE
ESTIMATED
AMOUNT
29
STOP SIGNS (MUTCD R1-1)
EACH
2
a� o
S�Q, 00
30
TRAFFIC CONTROL
L.S.
00
Soo • 00
31
SPEED LIMIT SIGNS (MUTCD R2-1)
EACH
2
BID TOTAL: $ � 79. 96
BID TOTAL: --i v.6 Ho vv,-" rirrY %vo 7 yovjAA�Dsix lav v��� S6v4,;7-s'
M Qr_ II)OD 1J, w; Y S/ x C�,v7s
(Written figure)
Unit Prices have been computed in accordance with paragraph 11.9.2 of the General
Conditions.
BIDDER acknowledges that quantities are not guaranteed and final payment will be
based on actual quantities determined as provided in the Contract Documents.
5. BIDDER agrees that the Work will be substantially complete within 180 calendar
days after the date when the Contract Times commences to run as provided in
paragraph 2.3 of the General Conditions, and completed and ready for final payment in
accordance with paragraph 14.13 of the General Conditions within 210 calendar days
after the date when the Contract Times commences to run.
BIDDER accepts the provisions of the Agreement as to liquidated damages in the event
of failure to complete the Work within the times specified in the Agreement.
6. The following documents are attached to and made a condition of this Bid:
(a) Required Bid Security in the form of bid bond or cashiers check.
.1
(b) Required BIDDER'S Qualification Statement with supporting data.
7. Communications concerning this Bid shall be addressed to:
Name �i2oNi4 �A 2Cc,2 Co,�C2�r� 2s , 1,�e .
Address 3x90 Sr,4:6 M 4144,j�-VV E , 61914'1 ,f , /7%D oI.?J6Y
(a) Performance and Payment Bonding Company
Nameyuj rED 4,,0-6 CASUAL rCom�An
Address -PD • fox 73 409 (26Z)A,e .'a SVD7
Agent\Power of Attorney Name (if used
Address
8. Terms used in the Bid which are defined in the General conditions or Instructions will
have the meanings indicated in the General Conditions or Instructions.
SUBMITTED on J Vm 6, 13 , 20 00.
State Contractor License No. Allo N
•
IF BIDDER IS:
An Individual
By
Doing business as
Business address:
Phone No.:
A Partnership
By
Business address:
Phone No.:
A Corporation
(Individual Name)
(Firm Name)
(General Partner)
By i iIWAJAO g96C2 LO AI C /,zc r�2S , 1n.�
(Corporation Name)
(State of Incorporation)
By 6XZA,7A1 Y. oAN,4,6,426 ee
(Name of Person Authorized to Sign)
Bi26S i o, -C A, 7 -
(Title) (Title)
Attest
/ U' (Corporate Sectary)
Business address: 3x90 S7;.7-6 //&j V, E
04/,/ �ejD&L . MO /,, X769
Phone No.: (x'73 ) .266 - 42 /
Date of Qualification to do business is
BF -7
(SEAL)
(SEAL)
(SEAL)
A Joint Venture
By (SEAL)
(Name)
Business address:
By (SEAL)
(Name)
Business address:
Phone Number and Address for receipt of official communications: a
(Each joint venturer must sign. The manner of signing for each individual, partnership and
corporation that is a party to the joint venture should be in the manner indicated above.)
BF -8
06-02-00 14:04 CITY OF CAPE GIRARDEAU ID= 1 573 651 0860 P.02
CITY OF CAPE GIRARDEAU
HOPPER ROAD PHASE I
From Mount Auburn Road to Kage Road
ADDENDUM #1
June 1, 2000
The following revisions have been made to the above named Contract Documents:
1. Item No. 4, Class "A" Excavation (Rock), shall be eliminated from the bid form. Rock excavation
will be paid at $50 per cubic yard. Rock quantity will be measured in the field by the project
inspector.
2. Item No. 31 will be added to the bid form. Item No. 31 will be two (2) Speed Limit signs (MUTCD
R2-1) to be paid as shown on the revised bid form.
3. Currently the project includes sidewalks on both the north and south sides of the street. The sidewalk
on the south side is to be eliminated. The bid form is adjusted accordingly.
The bid opening date will be changed to June 13, 2000, at 2:00 P.M. in the office of the City
Engineer.
This addendum trust be signed and attached to your Bid Documents.
bate 6 -/S-oZOoD
Un
UNITED FIRE & CASUALTY COMPANY
CEDAR RAPIDS, IOWA
BID BOND
Approz>cd by The American Institute of Arclidects, ALA- Document No. A 310 February 1970 Edition
Fronabarger Concreters, Inc.
KNOW ALL MEN BY TIAESE PRESENTS, that We .—
3290 State Hwy E, Oak Ridge, MO 63769
as Principal, hereinafter called the Principal,
and the UNITED FIRE & CASUALTY COMPANY, a corporation duly organized under the laws of the State of IOWA,
as Surety, hereinafter called the Surety, are held and firmly bound unto
401 Independence, Cape Girardeau, MO 63701
in the sum of *5% of Bid Amount
City of Cape Girardeau
as Obligee, hereinafter called the Obligee,
Dollar:
($ 85% of bid ), for the payment of which sum well and truly to be made, the said principal and the
said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these
presents.
WHEREAS, the Principal has submitted a bid for Hopper Road Extension Phase I
Now, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a contract with th,
Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or contrac
documents with good and sufficient surety for the faithful performance of such contract and for the prompt payment of labe
and material furnished in the prosecution thereof, or in the event of the failure of the Principal to enter such contract an(
give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof betweei
the amount specified in said bid and such larger amount for which the Obligee may in good faith contract with -another,, part
to perform the work covered by said bid, then this obligation shall be null and void, otherwise to remain `;> .�full forge an.
effect. jI �;r �.1
_
Signed and sealed this ----------- --------- — --- – 6th —day of _— JuneU .I
i. Co
- FRONABARGER CONCRETERS, INC.
- — (PRINCIPAL) !_ •' E{:
(W11 __ SI
dy r4j -
UNITED FIRE & CASUALTY C ,. � `
(SUR /5
(WITNESS)By
—1-111- u ri,mg4'p:Pf EY -IN -FACT)
ACKNOWLEDGMENT OF SURETY
State of Missouri
County of Cape Girardeau
On this 6th day of June 2000.
Personally appeared before me Priscilla B- Hunter who being duly sworn did depose and say that he/she is the
attorney-in-fact of the United Fire & Casualty Company of Cedar Rapids, Iowa, that the seal affixed to the attached instrument
is the Corporate Seal of said Corporation, and that said instrument was signed and sealed on behalf of said Corporation by
authority of its Board of Directors and the said Priscilla B. Hunter
acknowledged that he/she executed said instrument as such attorney-in-fact and as the free act and deed of said Corporation.
NANCY STRAUSER
Notary Public - Notary Seal
State of Missouri
Cape Girardeau County
My Commission ExpiIm,res Jun 20, 2003 Notary�Ubfic
ej,
UND-2031b
UNITED FIRE & CASUALTY COMPANY
HOME OFFICE - CEDAR RAPIDS, IOWA
CERTIFIED COPY OF POWER OF ATTORNEY
(Original on file at Honie Office of Company - See Certification)
KNOW ALL MEN BY TI IESE PRESEN'hS, 11U ,lie UNITED FIRE & CASUALTY COMPANY, a corporatioll duly organized and existing
under the laws of ,lie Stale of Iowa, and Ilaving its prillcipal office in Cedar Rapids, Slate of Iowa, does make, cco stitule and
appoint laves f t W. llEf 10 UI2 SIIAIZO14 GLASCU, OR ALAN 11. RAUSENBERGER,
OR
WILLIAM 'PALLMAN, LR, OIJUALL IL, OR 'POUD A. WARD, OR MARK A. GOODMAN,
Cllltl
ORPR1SC11,LA U. IIUN'1'[:R, UR '1'LE nUAt-1:5, CAC'G G1liAL2UEAU, MO,
ALL INDIVIDUALLY
of P O BOX 849 CARBONDALE IL 62903
giits true and lawful Atlorney(s)-ill -Fact with pvver �ls�lofusith(imilar`ralrule aslfollows sIA'NYeaIAND ALL IeBIbehalf all
lawful bonds, undertakings and other obligatory itstrunre
nl_IY COMPANY mrd all ,lie acts of said Attorney, pursuant to the authority
and to bind UNITED FIRE & CASUALTY COMPAN`�SUrebY'as luny and to the same extent as if such instruments were Signe Y
the duly authorized officers of UNITED FIRE- & unless sooner revoked.
hereby given are hereby ratified ar'rd confit med. 2001 the
The Authority hereby granted .shall expire MAY 6th
This power of Atlorlley is made and executed pursuant to and by authority of the following 8Y -Law duly adopted Y
Board of Directors of the Company on April 18, 1973.Builds and Undertakings•"
"Article V - Surely appoint
undertakings and other
Section 2, Appointment of JUloruey-In-roc,. "- Ile Presldeut or any vice Pres ldenl, or any other officer of the Conrpa'ta rbeyell afroffixed iby facsimile Po oily
by written certificates nitorneys-In4act to act la behalf of the Cul"Pany In Il�r execution of policies of lusurar lerbso used, being adopted by the
by written
certificInstfulliates of like nature. ilia slynalwe of Pity olllcer ouliturized ferebY. and the Corporate se Y
power of attorney or specinl powrr of ollonmy or err llllcnllan of ellher nulhorized hereby; such slgnalure and seal,
ave
Coagrauy as Ino url{, Inn, siyaadua of such nlllor and Ile orlylrrnl sent ul lin Cnmpnny, lu It, valid and binding upon Iia Comes of wllh the smoo force
and effect os Though aranuolly affixed. Such allorueys-In-loci, sublet, to flrr. Ihrdla0uns set forth In their respecllve certificates of auhgivall en to
lull power to bind lyre ol"PoaYd olby their lgrs tuieor y execution
oficer itl a Corry{nanny such rnrary nl ats ty fly lito ttle evoke altch tire apower andraull authority previously lo. The President
or any Vice President, ilia
any atior ey-la-fact.
� EUl=,lie UNIIEU FIRE & CASUALTY COMPANY has caused
IN WITNESS WIIEf1, these presents
uara�, to be signed by its assistant vice president and its corporate seal to be heretoA.D. affixed 9 is
6LIt day of MAY
COI101A1E�
UNITED FIRE &CASUALTY COMPANY .
39AL .1z
�wuu�� ii�r MY
Y/7AssistaVntVj
fePres"ident
State of Iowa, Counly of Llnn, ss: Clta in
that he is al
before tile personally came Jeffrey
On this 6t It day of MAY in and
& CASUALTY COMPANY, the cotporation described nstrumentNislcsuch corporate)
to me known, who being by rile duly swol(;Edid depose and say: that Ile resides in Cedar Rapids, State of owa;
Assistant Vice President of the UNITED F
above instrulnenh that Ito knows the seal of said corporation; prat the seal affixed to lie s ion.
as so affixed pursuant to authority given by the BoardofaDireacttors of °faldaid°cZEa,',
oation and that he signedhi
seal; that it w
name thereto pursuantto like authority, and acknowledges Same to be
MY cornnrission expires March 4 xh?� 20
4E.S j1IE1,1YL A. MCVAYSSIUN [XPIIIES CGITTIFICnfIUN
ch"21100
of the UNTIED FIRE & CASUALTY COMPANY, do hereby certify that 1 have compared the forth
in it
1, lire undersigned officer { u( the Secllon of lire BY -Laws of said Company as set forth in sa
copy of the Power of Attorney and affidavit, and the copy
and that the same are corre
Power of Attorney, V%vilh lite ORIGINALS ON PILE IN 11 IE ITOME OFFICE OF SAID COMPANY,
thereof, and of the whole of llrc said originals, and that the said Power of Attorney has not been re
a°kod the s
transcripts
now In lull force and e (f e'Ct.
;tclsuzny In leslin,olly wlreleof I have Ireleunlo subscribed 111y tra2000rid a Fixed lire corporate s
at
4 k1�k Company this 6th day of June
o COIf011liE � ,
kTl ^ • "'
ecrelar
V + 01
�Nuuratr
UNITED FIRE & CASUALTY COMPANY UNITED LITE INSURANCE COMPANY
118 SECOND AVENUE, S.E., P.O.BOX OX `3909 CEDAR RAPIDS, IOWA 52407
NOTICE TO MISSOURI SURETY BOND HOLDERS
Should you have a questions about your bond or policy, please contact your insurance agent first.
If you are unable to contact or obtain information from your agent, you may contact our company at
address and phone number below:
UNITED FIRE & CASUALTY COMPANY
ATTENTION: BOND DEPARTMENT
P.O. BOX 73909
CEDAR RAPIDS, IOWA 52407
1-800-343-9130
CITY OF CAPE GIRARDEAU
HOPPER ROAD EXTENSION
PHASE I
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
ON THE BASIS OF A STIPULATED PRICE
THIS AGREEMENT is dated as of the _..Jrq:?B day of �,� in the year
20t,bby and between the City of Cape Girardeau, Missouri (her ' after called OWNER)
and Fronabarger Concreters, Inc. (hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set
forth, agree as follows:
Article 1. WORK.
CONTRACTOR shall complete all Work as specified or indicated in the Contract
Documents. The Work is generally described as follows:
The work to be performed under these Contract Documents shall consist of
of all necessary grading, excavation and embankment construction, storm
sewers, drainage structures, construction of a seven-inch concrete pavement
with concrete curb and other related construction items necessary to
accomplish the work in accordance with the Plans and as stated in the
Specifications prepared by Bowen Engineering & Surveying, Inc. dated May,
2000.
This work is for the City of Cape Girardeau, Missouri.
Article 2. ENGINEER.
The City Engineer or his designee is to act as OWNER's representative, assume all duties
and responsibilities and have the rights and authority assigned to "ENGINEER" in the
Contract Documents in connection with completion of the Work in accordance with the
Contract Documents.
A-1
Article 3. CONTRACT TIMES.
3.1 The work will be substantially completed within one -hundred eighty (180) calendar
days after the date when the Contract Times commence to run as provided in paragraph
2.3 of the General Conditions, and competed and ready for final payment in accordance
with paragraph 14.13 of the General Conditions within two -hundred ten (210) days after the
date when the Contract Times commence to run.
3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the
essence of this Agreement and that OWNER will suffer financial loss if the Work is not
completed within the times specified in paragraph 3.1 above, plus any extensions thereof
allowed in accordance with Article 12 of the General Conditions. They also recognize the
delays, expense and difficulties involved in proving the actual loss suffered by OWNER if
the Work is not completed on time. Accordingly, instead of requiring any such proof,
OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a
penalty) CONTRACTOR shall pay OWNER Three -Hundred Dollars 300.00 for each
day that expires after the time specified in paragraph 3.1 for Substantial Completion until
the Work is substantially complete. After Substantial Completion, if CONTRACTOR shall
neglect, refuse or fail to complete the remaining Work within the time specified in paragraph
3.1 for completion and readiness for final payment or any proper extension thereof granted
by OWNER, CONTRACTOR shall pay OWNER _Three -Hundred Fifty Dollars ($ 350.00)
for each day that expires after the time specified in paragraph 3.1 for completion and
readiness for final payment.
Article 4. CONTRACT PRICE.
OWNER shall pay CONTRACTOR for completion of the Work in accordance with the
Contract Documents an amount in current funds equal to the sum of the amounts
determined pursuant to paragraph 4.2 below:
4.2 for all Unit Price Work, an amount equal to the sum of the established unit price for
each separately identified item of Unit Price Work times the estimated quantity of that item
as indicated in the bidding documents.
TOTAL OF ALL UNIT PRICES: Five hundred fifty-two thousand, six hundred seventy
nine dollars and ninety-six cent -0 552,679.96
As provided in paragraph 11.9 of the General Conditions estimated quantities are not
guaranteed, and determinations of actual quantities and classification are to be made by
ENGINEER as provided in paragraph 9.10 of the General Conditions. Unit prices have
been computed as provided in paragraph 11.9.2 of the General Conditions.
A-2
Article 5. PAYMENT PROCEDURES.
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER as
provided in the General Conditions.
5.1 Progress payments; Retainage. OWNER shall make progress payments on account
of the Contract Price on the basis of CONTRACTOR's Application for Payment as
recommended by ENGINEER, on or about the 10th day of each month during construction
as provided in paragraphs 5.1.1 and 5.1.2 below. All such payments will be measured by
the schedule of values established in paragraph 2.9 of the General Conditions (and in the
case of Unit Price Work based on the number of units completed) or, in the event there is
no schedule of values, as provided in the General Requirements.
5.1.1 Prior to Substantial Completion, progress payments will be made in an amount equal
to the percentage indicated below, but, in each case, less the aggregate of payments
previously made and less such amounts as ENGINEER shall determine, or OWNER may
withhold, in accordance with paragraph 14.7 of the General Conditions.
90% of Work completed (with the balance being retainage). If Work has
been 50% completed as determined by ENGINEER, and if the character and
progress of the Work have been satisfactory to OWNER and ENGINEER,
OWNER, on recommendation of ENGINEER, may determine that as long as
the character and progress of the Work remain satisfactory to them, there will
be no additional retainage on account of Work completed, in which case, the
remaining progress payments prior to Substantial Completion will be an
amount equal to 100% of the Work completed.
90% (with the balance being retainage) of materials and equipment not
incorporated in the Work (but delivered, suitably stored and accompanied by
documentations satisfactory to OWNER as provided in paragraph 14.2 of the
General Conditions).
5.1.2 Upon Substantial Completion, in an amount sufficient to increase total payments to
CONTRACTOR to 95% of the Contract Price (with the balance being retainage), less such
amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with
paragraph 14.7 of the General Conditions.
5.2 Fina/ Payment. Upon final completion and acceptance of the Work in accordance with
paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the
Contract Price as recommended by ENGINEER as provided in said paragraph 14.13.
A-3
Article 6. INTEREST.
All moneys not paid when due as provided in Article 14 of the General Conditions shall bear
interest at the maximum rate allowed by law at the place of the Project.
Article 7. CONTRACTOR'S REPRESENTATIONS.
In order to induce OWNER to enter into the Agreement, CONTRACTOR makes the
following representations:
7.1 CONTRACTOR has examined and carefully studied the Contract Documents
(including the Addenda listed in paragraph 8) and the other related data identified in the
Bidding Documents, including "technical data".
7.2 CONTRACTOR has visited the site and become familiar with and is satisfied as to the
general, local and site conditions that may affect cost, progress, performance and
furnishing of the Work.
7.3 CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws
and Regulations that may affect cost, progress, performance and furnishing of the Work.
7.4 CONTRACTOR acknowledges that OWNER and ENGINEER do not assume
responsibility for the accuracy or completeness of information and data shown or indicated
in the Contract Documents with respect to Underground Facilities at or contiguous to the
site. CONTRACTOR has obtained and carefully studied (or assumes responsibility for
having done so) all such additional supplementary examinations, investigations,
explorations, tests, studies and data concerning conditions (surface, subsurface and
Underground Facilities) at or contiguous to the site or otherwise which may affect cost,
progress, performance or furnishing of the Work or which relate to any aspect of the
means, methods, techniques, sequences and procedures of construction to be employed
by CONTRACTOR and safety precautions and programs incident thereto. CONTRACTOR
does not consider that any additional examinations, investigations, explorations, tests,
studies or data are necessary for the performance and furnishing of the Work at the
Contract Price, within the Contract Times and in accordance with the other terms and
conditions of the Contract Documents.
7.5 CONTRACTOR is aware of the general nature of work to be performed by OWNER
and others at the site that relates to the Work as indicated in the Contract Documents.
7.6 CONTRACTOR has correlated the information known to CONTRACTOR, information
and observation obtained from visits to the site, reports and drawings identified in the
Contract documents and all additional examinations, investigations, explorations, tests,
studies and data with the Contract Documents.
7.7 CONTRACTOR has given ENGINEERwritten notice of all conflicts, errors, ambiguities
or discrepancies that CONTRACTOR has discovered in the Contract Documents and the
A-4
written resolution thereof by ENGINEER is acceptable to CONTRACTOR, and the Contract
Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.
Article 8. CONTRACT DOCUMENTS.
The Contract Documents which comprise the entire agreement between OWNER and
CONTRACTOR concerning the Work consist of the following:
8.1 This Agreement (pages 1 to 7 inclusive).
8.2 Exhibits to this Agreement (pages _ to _, inclusive).
8.3 Performance, Payment, and other Bonds, identified as exhibits _ and consisting
of _ pages.
8.4 Notice to Proceed.
8.5 General Conditions (pages 1 to 55 , inclusive, Available upon request).
8.6 Supplementary Conditions (pages SCA to SC -5, inclusive).
8.7 Specifications bearing the title HOPPER ROAD EXTENSION PHASE I.
8.8 Standard Specifications for Street Improvements and Sidewalk Improvements
(Available upon request).
8.9 Drawings.
8.10 Addenda numbers 1 to _, inclusive.
8.11 CONTRACTOR's Bid (pages BF -1 to BF -8 , inclusive) marked exhibit A .
8.12 Documentation submitted by CONTRACTOR prior to Notice of Award (pages to
_, inclusive).
8.13 The following which may be delivered or issued after the Effective Date of the
Agreement and are not attached hereto: All Written Amendments and other documents
amending, modifying or supplementing the Contract Documents pursuant to paragraphs
3.5 and 3.6 of the General Conditions.
The documents listed in paragraphs 8.2 et seq. above are attached to this Agreement
(except as expressly noted otherwise above).
A-5
There are no Contract Documents other than those listed above in the Article 8. The
Contract Documents may only be amended, modified or supplemented as provided in
paragraphs 3.5 and 3.6 of the General Conditions.
Article 9. MISCELLANEOUS.
9.1 Terms used in this Agreement which are defined in Article 1 of the General Conditions
will have the meanings indicated in the General Conditions.
9.2 No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of the party
sought to be bound; and, specifically but without limitation, moneys that may become due
and moneys that are due may not be assigned without such consent (except to the extent
that the effect of this restriction may be limited by law), and unless specifically stated to the
contrary in any written consent to an assignment no assignment will release or discharge
the assignor from any duty or responsibility under the Contract Documents.
9.3 OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and
legal representatives to the other party hereto, its partners, successors, assigns and legal
representatives in respect to all covenants, agreements and obligations contained in the
Contract Documents.
9.4 Any provision or part of the Contract Documents held to be void or unenforceable
under any Law or Regulation shall be deemed stricken, and all remaining provisions shall
continue to be valid and binding upon OWNER and CONTRACTOR, who agree that the
Contract Documents shall be reformed to replace such stricken provision or part thereof
with a valid and enforceable provision that comes as close as possible to expressing the
intention of the stricken provision.
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed the Agreement in
multiple copies, One counterpart each has been delivered to CONTRACTOR and
ENGINEER and two counterparts to the OWNER. All portions of the Contract Documents
have been signed, initialed or identified by OWNER and CONTRACTOR or identified by
ENGINEER on their behalf.
This Agreement will be effective on , 20L�>(which is the Effective Date of
the Agree mer t).
OWNER
IM
CONTRACTOR Fronabarger Concreters, Inc.
r� ! [CORPORATE SEAL] [gORPORATE Sf�IL]
Attest Attest
Address for 4ving notices Addre s for giving notices
401 Independence Street 3290 State Highway E
Cape Girardeau, MO 63702
(If OWNER is a public body, attach
evidence of authority to sign and
resolution or other documents
authorizing execution of Agreement.
Oak Ridge, MO 63769
License No.
Agent for service of process:
(If CONTRACTOR is corporation, attach
evidence of authority to sign.)
A-7
EXHIBIT A
CITY OF CAPE GIRARDEAU
HOPPER ROAD EXTENSION
PHASE
BID FORM
(EJCDC 1910-18) (1990)
PROJECT IDENTIFICATION: The work to be performed under these Contract
Documents consists of all necessary grading, excavation and embankment construction,
storm sewers, drainage structures, construction of a seven-inch concrete pavement with
concrete curb and other related construction items necessary to accomplish the work in
accordance with the Plans, and as stated in the Specifications and Contract Documents
for this Project. The work is for the City of Cape Girardeau, Missouri.
THIS BID IS SUBMITTED TO: CITY OF CAPE GIRARDEAU, MO
401 INDEPENDENCE STREET
CAPE GIRARDEAU, MO P3702-0617
1. The undersigned BIDDER proposes and agrees, if the Bid is accepted, to enter into an
agreement with OWNER in the form included in the Contract Documents to perform and
furnish all Work as specified or indicated in the Contract Documents for the Bid Price and
within the Bid Times indicated in this Bid and in accordance with the other terms and
conditions of the Contract Documents.
2. BIDDER accepts all of the terms and conditions of the Advertisement or Invitation to Bid
and Instructions to Bidders, including without limitation those dealing with the disposition
of Bid security. This Bid will remain subject to acceptance for thirty-five days after the day
of Bid opening. THE BIDDER will sign and deliver the required number of counterparts of
the Agreement with the Bonds and other documents required by the Bidding Requirements
within fifteen days after the date of OWNER'S notice of Award.
3. In submitting this Bid, BIDDER represents, as more fully set forth in the Agreement, that:
(a) BIDDER has examined and carefully studied the Bidding Documents and the
following Addenda, receipt of all which is hereby acknowledged: (List Addenda by
Addendum Number and Date)
BF -1
(b) BIDDER has visited the site and become familiar with and is satisfied as to the general,
local and site conditions that may affect cost, progress, performance and furnishing of the
Work;
(c) BIDDER is familiar with and is satisfied as to all federal, state and local Laws and
Regulations that may affect cost, progress, performance and furnishing of the Work.
(d) BIDDER acknowledges that OWNER and Engineer do not assume responsibility for
accuracy or completeness of information and data shown or indicated in the Bidding
Documents with respect to Underground Facilities at or contiguous to the site. BIDDER
has obtained and carefully studied (or assumes responsibility for having done so) all such
additional or supplementary examinations, investigations, explorations, tests, studies and
data concerning conditions (surface, subsurface and Underground Facilities) at or
contiguous to the site or otherwise which may affect cost progress, performance or
furnishing of the Work or which relate to any aspect of the means, methods, techniques,
sequences and procedures of construction to be employed by BIDDER and safety
precautions and programs incident thereto. BIDDER does not consider that any additional
examinations, investigations, explorations, tests, studies or data are necessary for the
determination of this Bid for performance and furnishing of the Work in accordance with the
times, price and other terms and conditions of the Contract Documents.
(e) BIDDER is aware of the general nature of Work to be performed by Owner and
others at the site that relates to Work for which this Bid is submitted as indicated in the
Contract Documents.
(f) BIDDER has correlated the information known to BIDDER, information and
observations obtained from visits to the site, reports and drawings identified in the Contract
Documents and all additional examinations, investigations, explorations, tests, studies and
data with the Contract Documents.
(g) BIDDER has given Engineer written notice of all conflicts, errors, ambiguities or
discrepancies that BIDDER has discovered in the Contract Documents and the written
resolution thereof by ENGINEER is acceptable to BIDDER, and the Contract Documents
are generally sufficient to indicate and convey understanding of all terms and conditions
for performing and furnishing the Work for which this Bid is submitted.
(h) This Bid is genuine and not made in the interest of or on behalf of any undisclosed
person, firm or corporation and is not submitted in conformity with any agreement or rules
of any group association, organization or corporation; BIDDER has not directly or indirectly
induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not
solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER
has not sought by collusion to obtain for itself any advantage over any other Bidder or over
OWNER.
(i) (Any other representation required by Laws and Regulations.)
BF -2
4. BIDDER will complete the Work in accordance with the Contract Documents for the
following price(s):
BF -3
Unit Price Bid
Hopper Road Extension, Phase I
Cape Girardeau Missouri
NO
ITEM
UNIT
EST.
QTY
UNIT
PRICE
ESTIMATED
AMOUNT
1
REMOVE EXISTING IMPROVEMENTS
L.S.
1
l 1, 000.00
ll, 000, DO
2
CLEARING &GRUBBING
ACRES
3.32
3
CLASS "B" EXCAVATION
CU. YD
51,144
!, 4S'
3$%• 60
4
499
—
—
5
SPOIL
CU. YD
16,676
OD
6
7" P.C. CONCRETE PAVEMENT
SQ. YD
14,381•
1 g • OV
73,.2 3 9• 40.67
4" TYPE "V" AGGREGATE BASE
Q. YD
15,174.
� • �a
oZ � �(f , DD
8
6- GRADE 'B' SURFACE AGGREGATE
SQ. YD
94
/.470
0.0
9
2" BITUMINOUS PAVEMENT, BP-1
TON
8
SD, OD
40-6010
5" BITUMINOUS BASE MATERIAL
TON
21
00
/ DSO.OD
11
PRIME COAT
GAL.
74
16-00
9;.A. OD
12
4" P.C. CONCRETE SIDEWALK
SQ. YD
1,541
'110,60
3D �0 • D�
13
4' DIA. JUNCTION MANHOLE
EACH
2
1x00.00
vZ DO.DD
14
3'-6"X 3'-0" SINGLE CURB INLET
EACH
11
1 '940.'00
15
4'-0" X 4'-0" SINGLE CURB INLET
EfKCH
2
/ b00.00
a DOO. DO
16
5'-0" X 4'-0" SINGLE CURB INLET
EACH
1
QD
j� �jD• pp
17
3'-0" X 3'-0" GRATED INLET
E4CH
1
•OD
A a-5' • DO
18
15" R.C.P.
L.F.
159
/7.40
7
19
18" R.C.P.
L.F.
491
! � • G �
I j 7 / • �g
20
18" F.E.S.
EACH
6
60. DD
21
REMOVE AND RELAY EXISTING 18"
F.E.S.
EACH
1
pe) 00
/00.00
22
24" R.C.P.
L.F.
680.5
oZ5 776-'
7 S� , 8'923
24" F.E.S.
EACH-2
30.00
lv d • DO
24
30" R.C.P.
L.F.
136.5
, D
W.'060
25
30" F.E.S.
EACH
2
,4a5.�0
��•OD
26
RIP RAP IN PLACE (18" THICK)
SQ. YD
244
J40.60
27
FERTILIZER, SEEDING, &MULCHING
ACRES
5.5
1 -�06 • OD
16 X000 • DO
28
EROSION CONTROL
L.S.
1
7,046-00
7DOD•DD
BF-4
NO
ITEM
UNIT
EST.
QTY
UNIT
PRICE
ESTIMATED
AMOUNT
29
STOP SIGNS (MUTCD R1-1)
EACH
2
V. DO
a8
5-4,0.00
30
TRAFFIC CONTROL
L.S.
1
���, 00
5�D0 • DO
31
SPEED LIMIT SIGNS (MUTCD R2-1)
EACH
2
BID TOTAL: $ (lo 79. 96
BID TOTAL: -�i V� NUnIVKED �FrY %p �HDy�SAAJ-[7, Six h�v�v�y S�v��vrs�
N. QC- 4 A�D NJ "TY Y/ x Ce",vY
(Written figure)
BF -5
Unit Prices have been computed in accordance with paragraph 11.9.2 of the General
Conditions.
BIDDER acknowledges that quantities are not guaranteed and final payment will be
based on actual quantities determined as provided in the Contract Documents.
5. BIDDER agrees that the Work will be substantially complete within 180 calendar
days after the date when the Contract Times commences to run as provided in
paragraph 2.3 of the General Conditions, and completed and ready for final payment in
accordance with paragraph 14.13 of the General Conditions within 210 calendar days
after the date when the Contract Times commences to run.
BIDDER accepts the provisions of the Agreement as to liquidated damages in the event
of failure to complete the Work within the times specified in the Agreement.
6. The following documents are attached to and made a condition of this Bid:
(a) Required Bid Security in the form of bid bond or cashiers check.
(b) Required BIDDER'S Qualification Statement with supporting data.
7. Communications concerning this Bid shall be addressed to:
Name rRon.),4XbA2C,4re
Address 3A9O Sr.4 %6 1t% 6jV4-jf-M E , 6ke 2, Dz-,z , f%D G 376 q
(a) Performance and Payment Bonding Company
Name -000 --ED 1�',Ie6 � CAsv,41.7-V aM1O'1A*
Address PO • max 73 9409 CEnA,e ii 7,0 Ds locus .3a Slo7
Agent\Power of Attorney Name (if used
Address
8. Terms used in the Bid which are defined in the General conditions or Instructions will
have the meanings indicated in the General Conditions or Instructions.
SUBMITTED on .� uti� 13 , 2000.
State Contractor License No. /Ilo N c--
MW
IF BIDDER IS:
An Individual
By
Doing business as
Business address:
Phone No.:
A Partnership
2
Business address:
Phone No.:
A Corporation
(Individual Name)
(Firm Name)
(General Partner)
(SEAL)
(SEAL)
By �i[O�JA�lRRGi2 (�6Aj c 2f r ies , jx-y (SEAL)
(Corporation Name)
(State of Incorporation)
By 6.C4,VV f-.PONA,6.42G ee
(Name of Person Authorized to Sign)
Attest
-Pi2,6.S 10r- N 7 -
(Title) (Title)
(Corporate Se
Business address: 3eZ90 S7,V7-6 11w f>,
_J;?,1)C.L, mo ��769
Phone No.:573) a1.6 - 4,7 / d2
Date of Qualification to do business is 5Q
MM
i;41
J 0 4.
A Joint Venture
M
(Name)
Business address:
(SEAL)
BY (SEAL)
(Name)
Business address:
Phone Number and Address for receipt of official communications:
(Each joint venturer must sign. The manner of signing for each individual, partnership and
corporation that is a party to the joint venture should be in the manner indicated above.)
ME
06-02-00 14:04 CITY OF CAPE GIRARDEAU ID= 1 573 651 0860 P.02
CITY OF CAPE GIRARDEAU
HOPPER ROAD PHASE I
From Mount Auburn Road to mage Road
ADDENDUM #1
June 1, 2000
The following revisions have been made to the above named Contract Documents:
1. Item No. 4, Class "A" Excavation (Rock), shall be eliminated from the bid form. Rock excavation
will be paid at $50 per cubic yard. Rock quantity will be measured in the field by the project
inspector.
2. Item No. 31 will be added to the bid form. Item No. 31 will be two (2) Speed Limit signs (MUTCD
R2-1) to be paid as shown on the revised bid form.
3. Currently the project includes sidewalks on both the north and south sides of the street. The sidewalk
on the south side is to be eliminated. The bid form is adjusted accordingly.
The bid opening date will be changed to June 13, 2000, at 2:00 P.M. in the office of the City
Engineer.
This addendum must be signed and attached to your Bid Documents.
bate
0
UNITED FIRE & CASUALTY COMPANY
CEDAR RAPIDS, IOWA
BID BOND
Appro d by The American Institute of Architects, AI.A Document No. A 310 February 1970 Edition
KNOW ALL MEN BY THESE PRESEN'i5, that we
Fronabarger Concreters, Inc.
3290 State Hwy E, Oak Ridge, MO 63769
as Principal, hereinafter called the Principal,
and the UNITED FIRE & CASUALTY COMPANY, a corporation duly organized under the laws of the State of IOWA,
City of Cape Girardeau
as Surety, hereinafter called the Surety, are held and firmly bound unto
401 Independence, Cape Girardeau, MO 63701
as Obligee, hereinafter called the Obligee,
in the sum of
*5% of Bid Amount Dollars
($ 85% of bid ), for the payment of which sum well and truly to be made, the said principal and the
said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these
presents.
WHEREAS, the Principal has submitted a bid for Hopper Road Extension Phase I
Now, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a contract with the
Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or contract
documents with good and sufficient surety for the faithful performance of such contract and for the prompt payment of labor
and material fumished in the prosecution thereof, or in the event of the failure of the Principal to enter such contract and
give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof between
the amount specified in said bid and such larger amount for which the Obligee may in good faith contract w1. it4: anbther;,party
en this obligation shall be null and void, otherwise to remain u f • M force and
to perform the work covered by said bid, th
effect.
Signed and sealed this __ 6th _ __ day of June - :� i A DJ I .
- --- —
c)J �f
- FRONABARGER CONCRETERS, INC. ��. al)
(PRINCIPAL)
Wl SS)
r( r
- ����y (wlrNrSsl
By P -- .
Pricrilla B. Hun(£
UALTY G4WIPAM(r (sea
-FACr)
ACKNOWLEDGMENT OF SURETY
State of Missouri
County of Cape Girardeau
On this 6th day of .Tune 2000.
Personally appeared before me Priscilla B. Hunter who being duly sworn did depose and say that lie/she is the
attorney-in-fact of the United Fire & Casualty Company of Cedar Rapids, Iowa, that the seal affixed to the attached instrument
is the Corporate Seal of said Corporation, and that said instrument was signed and sealed on behalf of said Corporation by
authority of its Board of Directors and the said Priscilla B. Hunter
acknowledged that he/she executed said instrument as such attorney-in-fact and as the free act and deed of said Corporation.
---------- A6
NANCY STRAUSER
Notary Public - Notary Seal AA
State of Missouri
Cape Girardeau County
My Commission Expires Jun 20, 2003 Notary ublic
UND-2031b
's
UNITED FIRE & CASUALTY COMPANY
HOME OFFICE - CEDAR RAPIDS, IOWA
CERTIFIED COPY OF POWER OF ATTORNEY
Un (Original on file at Horne Office of Company - See Certification)
Ileal the UNITED F-1111 & CASUAL-lY COMPANY, a corporation duly organized and existing
KNOW ALL MEN BY THESE PRESENTS,
its principal office in Cedar Rapids, Slate of Iowa, does make, constitute and
under the laws of the Stale of Iowa, and having
l2AUSENBERGER, OR
appoint CHARLES W. DECKER, OR SHARON GLASCO, OR ALAN ll.
WILLIAM TALLMAN, CARBONDALE, IL, OR 'TODD A. WARD, OR MARK A. GOODMAN,
OR PRISCILLA D. IIUN'TGR, Up Cllltl:J'1'lG AUAt1:1, CAL'13 GILZARDEAU, MO,
ALL INDIVIDUALLY
of P O BOX 649 CARBONDALE IL 62903
ll
its true and lawful Allorney(s)-ill -F-act with Power and authority hereby cos fond to siA,NYeaIANID ALL'teB1ONDSbehalf a
lawful bonds, undertakings and other obligatory instrunlents of similar nature as follows:
such
truments
re
gned by
as
and to bind UNITED FIRE & CASUALTY CUMPA&N�nsU^�.I Yas fully and COMP ANY atidthe
all tilesame
acts extent
saidlfAttorneys pu suant oe tile sta thoritty
the duly authorized officers of UNITED FIRE
hereby given are hereby ratified and confirmed. 2001 unless sooner revoked.
The Authority hereby granted shall expire MAY 6 t Il
This power of Attorney is made and executed Pursuant to and by authority of the following By -Law duly adopted by the
Board of Directors of lite Company on April 18, 1973.
"Article V - Surely Bonds and Undertakings." appoint
Secllorl 2, p{ undertakings and other
A rolnbuenl of Alloney.lmrocl, "-Ihr presldral or Any Vice Presldem, or any other officer of the Company, may, born Ilene to t me, PP
by written certificates attorneys -lo fact to act hr behall of lie colorin In ihr execution of policies of Insu01, rance, bonds, beate se le ado ted by the
poweatorOtto rtr meet of llike
ke warnature.
thernYyoratto lllcollon of tildeicer , nuthorlled rleeeby s1uchlseyCnlu er and seal, rwher so used by 9afile lie to any
Congrnuy ns Tho mlpinal slynalw" of such officer nad the mfylnnl sial ul Ilm Conq urny, to hr valid and bindlny ulve Tho Company with lire steel force
and effect as though manually alllxed. Such otlornrys-In-loci, sub)rcl to
Ihr. Ihullaliuns set Imlh In llrelr respective certificates of authority shelf
to
ts
lull power to Vice Pries tire
1, their
or1e and any
otherullon 01 01 ry such te a Couyrauyrnraly aaa,Y/lure evoke all itach tile apowt ol er ahe nd1au11 authority Previously 9 President
ora y
any attorney-in.lacl.
� FIRE- CASUALI Y COMPANY has caused these Presents
IN WITNESS WIIE1tEUl=, rile UNI I EDhereto
tr,a„nr� to be signed by its assistant vice president and its corporate seal to be here A affixed f19 99is
t
6tit day of MAY
o COItOtAIE
UNITED FIRE &CASUALTY COMPANY
fiZAL '
•,; (v(/
By
Assistant VVfe
sident
State of Iowa, County of Llan, ss:
an
On this 6 t It day of MAY 3.999. before the Pesonally came Jeffrey A. Chaplovva; that he in
to me known, who being by file duly sworn, did depose and
COMPLANYhat !1Qtl a scorrporatioides in e� dear scribed Snatand fwh ch executed s the
ed
Assistant Vice President of the UNTIED FIRE & to
above instrufn6nl; that ho knows lite seal of said corporation; lite lBoard hat eof eDirectorsd of said corporation and 1 that u he ch signed corathis
seal; that it was so affixed pursuant to authority give Y
ration. fi��
name thereto pursuant to like authority, and acknowledges sante to be lite act and deed of said co �� 1 ► t WCu
Notary P tic C
My commission expires March 4
xh8 20C
[j.-J7RyL�MCVy1YMISSIONExpinES CEIIIIFICAIION
ardi 4, 2( ie
the fore9oinf
i, the undersigned officer of tie UNITED FIRE & CASUALTY COMPANY, do hereby certify that I have come set in saic
copy of the Power of r,,tollley and affidavit, and the clll'IE IrIOME OFFotile IICE OF -on of IISAID COMPANY,le By-Lavvs of aland othat af he ssame farehcorrec
Power of Attorney, "ill, life ORIGINALS ON FILE IN
transcripts thereof, and of he whole of the said originals, and that the said Power of Attorney has not vseaen lof and `
the sa
now In lull force and ef(e'cl.
el„cJ'bUa4i In l
(�eslintony whereof I have heleuno subscribed my pante and a Fi ed rile corporate
�� Company this 6th day of June 1$d 2000
Q C01101A1E
BILL 4� ecretary
01
�'�+Nuu,Ntr
UNITED FIRE & CASUALTY COMPANY UNITED LIFE INSURANOE COMPANY
11$ SECOND AVENUE, S.Er, P.O. $OX 73909 CEDAR RAPIDS, IOM -1 52407
NOTICE TO MISSOURI SURETY BOND HOLDERS
Should you have a questions about your bond or policy, please contact your insurance agent first.
If you are unable to contact or obtain information from your agent, you may contact our company at
address and phone number below:
UNITED FIRE & CASUALTY COMPANY
ATTENTION: BOND DEPARTMENT
P.O. BOX 73909
CEDAR RAPIDS, IOWA 52407
1-800-343-9130
CHANGE ORDER # 1
PROJECT TITLE HODDer Road Phase 1
CONTRACT DATE July 18`h, 2000
CONTRACTOR Fronabarger Concreters, Inc
The following changes are hereby made to the Contract Documents:
Additional excavation and installation of rock to firm up the subgrade in the cut from
station 24+50 to 26+50.
Part 1: Changes to bid items.
Chanaed from:
NO.
ITEM
UNIT
EST. QTY.
I UNIT PRICE
EST. PRICE
3
CLASS "B" EXCAVATION
I C.Y.
151,144
1$1.65
$ 84,387.60
Chanaed to:
NO.
ITEM
UNIT
EST. QTY.UNIT
PRICE
EST. PRICE
3
1 CLASS "B" EXCAVATION
I C.Y.
151,432 d
$ 1.65
$ 84,862.80
Part 2: Additional contract items.
NO.
ITEM
I UNIT
I EST. QTY.
I UNIT PRICE
I EST. PRICE
32
ROCK FILL
I TONS
1432.30
$ 7.50
$ 3242.25
JUSTIFICATION
After the excavation was made for the roadway it was discovered that the subgrade
within the cut was too wet and soft for concrete placement. In order to obtain needed
compaction the subgrade was excavated an additional two feet and rock was hauled in.
This work is in addition to the bid quantities, therefore the contractor should be reimbursed
at the bid unit price.
CHANGE TO CONTRACT PRICE
Original contract price:
$ 552,679.96
Page 1 of 2
Current contract price as adjusted by previous change orders:
$ 552,679.96
Current contract price due to this change order will be increased by:
$ 3,717.45
The new contract price due to this change order will be:
$ 556,397.41
CHANGE TO CONTRACT TIME
There will be no change to the contract time in this change order.
APPROVALS REQUIRED:
To be effective, this Change Order must be approved by the Owner if it changes the scope
or objective of the project, or may otherwise be required under the terms of the
Supplementary General Conditions to the Contract.
Recommended. by
i
Approvdd by
Approved
v
Date �- -2-5�`&�—
roject Manager
--�^ Date
itv Enaineer
Date O
/YIi�NpEL /n�cc.�,E' l
City Manager
Accepted by Date
ro abarger Con eters, Inc.
Change Order #1
Hopper Road Phase I
Page 2 of 2
CHANGE ORDER # 2
PROJECT TITLE Hopper Road Extension Phase 1
CONTRACT DATE July 18, 2000
CONTRACTOR Fronabarger Concreters, Inc.
The following changes are hereby added to the Contract Documents:
CHANGE FROM:
The contract document, through Addendum 1, includes a unit price for
encountered rock but does not include a quantity.
CHANGE TO:
ITEM NO.
ITEM
UNIT
QUANTITY
UNIT PRICE
AMOUNT
32
Class 'A' Rock
C.Y.
1961.89
$ 50.00 $
98,094.50
JUSTIFICATION
Excavation for Class 'A' Excavation was intentional deleted from the
bid form because the quantity of rock that would be encountered was
unknown. However, a unit price was established at $50 a cubic yard.
CHANGE TO CONTRACT PRICE
Original contract price:
$ 552,679.96
Current contract price as adjusted by previous change orders:
$ 556,397.41
Current contract price due to this change order will be increased by:
$ 98,094.50
The new contract price due to this change order will be:
$ 654,491.91
Change Order # 2
Hopper Road Extension, Phase I
Page Two of Two
CHANGE TO CONTRACT TIME
There will be no days added to the contract time in this change order.
APPROVALS REQUIRED:
To be effective, this Change Order must be approved by the Owner if
the changes the scope or objective of the project, or may otherwise be
required under the terms of the Supplementary General Conditions to the
Contract.
Recommended by
FZ
ject Manager
City Engineer
Date //y—
Date i t _ Z-'-06
Date
Approved by /eH E
City ager
Accepted by Date
Fo ro abarger C creters, Inc.
CHANGE ORDER #3
PROJECT TITLE Hopper Road Phase I
CONTRACT DATE July 18, 2000
CONTRACTOR Fronabarger Concreters, Inc.
The following changes are hereby made to the Contract Documents:
Item 1: Changes to bid items
Changed from:
Item
Unit
Qty.
Unit Price
No.
Item
Unit
Qty.
Unit Price
Price
13.
4' Junction Manhole
EA
2
$1,200.00
$ 2,400.00
14.
3'-6"x3'-0" Single Curb
EA
11
$1,800.00
$19,800.00
$ 750.00
Inlet
inlet
17.
3'-0"x3'-0" Grated Inlet
EA
1
$2,250.00
$ 2,250.00
32.
Class "A" Rock Excavation
CY
1,961.89
$ 50.00
$98,094.50
Changed
to:
Seed & straw
AC
0.1
$10,000.00
No.
Item
Unit
Qty.
Unit Price
Price
13.
4' Junction Manhole
EA
3
$1,200.00
$ 3,600.00
14.
3'-6"x3'-0" Single Curb
EA
12
$1,800.00
$ 21,600.00
Inlet
17.
3'-0"x3'-0" Grated Inlet
EA
0
$2,250.00
$ 0.00
32.
Class "A" Rock Excavation
CY
2008
$ 50.00
$100,400.00
Item 2: Additional contract items
No.
Item
Unit
Qty.
Unit Price
Price
33.
15" RCP
LF
305.0
$33.00
$10,065.00
34.
4'x4' Area Inlet
EA
1
$1,200.00
$ 1,200.00
35.
Connection to existing
EA
1
$750.00
$ 750.00
inlet
36.
Remove and replace
SY
68.54
$49.50
$ 3,392.73
driveway pavement
37.
Seed & straw
AC
0.1
$10,000.00
$ 1,000.00
JUSTIFICATION
This change order includes items to construct a storm sewer to drain a portion of
the Pheasant Cove area. Two residences were have stormwater problems as a result of
the Hopper Road construction. The City decided to construct an area inlet and piping to
carry a majority of the water to an existing storm sewer along Pheasant Cove. The
contract included an item for 15" RCP that was constructed in an undeveloped area. The
15" RCP pipe in item 33 was constructed between two houses in close proximity and
extra care was needed to avoid damaging structures in the area. The same holds true for
item 37, seed & straw. There was a change in the alignment of the driveway at Ford &
Sons Funeral Home. This change eliminated the grated inlet, Item No. 17 and added
another single curb inlet increasing Item No. 14 to 12. While grading the 3:1 slopes,
additional rock was encountered that had to be excavated which increases the quantity of
Class 'A' excavation.
CHANGE TO CONTRACT PRICE
Original contract price:
$552,679.96
Current contract price as adjusted by previous change orders:
$654,491.91
Current contract price due to this change order will be increased by:
$ 19,463.23
The new contract price due to this change order will be:
$673,955.14
CHANGE TO CONTRACT TIME
Original contract time:
Substantial completion time — 180 calendar days - January 27, 2001
Final completion time — 210 days - February 26, 2001
Current contract time as adjusted by previous change orders:
No change
Current contract time due to this change order will be increased by:
No change
APPROVALS REQUIRED:
To be effective, this Change Order must be approved by the Owner if it changes
the scope or objective of the project, or may otherwise be required under the terms of the
Supplementary General Conditions to the Contract.
Recommended by Q Date
Mar, . Lester, City"Engineer
?T)flojn�L Date 424?, V 0/
Mela&Q Gertis, Project Manager
Approved by Date
Michael G. Miller City Manager
er
Accepted by Date
Fronabarger oncreters, IV
W
CHANGE ORDER #4 & FINAL
PROJECT TITLE Hopper Road Phase I
CONTRACT DATE July 18, 2000
CONTRACTOR Fronabarger Concreters, Inc.
The following changes are hereby made to the Contract Documents:
Item 1: Changes to bid items
Changed from:
No.
Item
Unit
Qty.
Unit Price
Price
3.
Class "B" Excavation
CY
51,432
$1.65
$84,862.80
5.
Spoil
CY
16,676
$2.50
$41,690.00
6.
7" P.C. Concrete Pavement
SY
14,381
$19.00
$273,239.00
7.
4" Type "V" Agg. Base
SY
15,174
$1.50
$22,761.00
8.
6" Grade "B" Surface Agg.
SY
94.0
$1.50
$141.00
9.
2" Bituminous Pavement
Ton
8.0
$50.00
$400.00
10.
5" Bituminous Base Matl.
Ton
21.0
$50.00
$1,050.00
11.
Prime Coat
Gal
74.0
$3.00
$222.00
12.
4" P.C. Concrete Sidewalk
SY
1,541
$20.00
$30,820.00
18.
15" RCP
LF
159
$17.40
$2,766.60
19.
18" RCP
LF
491.0
$18.68
$9,171.88
22.
24" RCP
LF
680.5
$25.75
$17,522.88
24.
30" RCP
LF
136.5
$32.00
$4,368.00
Changed to:
No.
Item
Unit
Qty.
Unit Price
Price
3.
Class "B" Excavation
CY
56,699
$1.65
$93,553.35
5.
Spoil
CY
16,437
$2.50
$41,092.50
6.
7" P.C. Concrete Pavement
SY
14,778.4
$19.00
$280,789.60
7.
4" Type "V" Agg. Base
SY
15,522.0
$1.50
$23,283.00
8.
6" Grade `B" Surface Agg.
SY
88.0
$1.50
$132.00
9.
2" Bituminous Pavement
Ton
0.0
$50.00
$0.00
10.
5" Bituminous Base Matl.
Ton
0.0
$50.00
$0.00
11.
Prime Coat
Gal
0.0
$3.00
$0.00
12.
4" P.C. Concrete Sidewalk
SY
1,510.8
$20.00
$30,216.00
18.
15" RCP
LF
166.0
$17.40
$2,888.40
19.
18" RCP
LF
516.0
$18.68
$9,638.88
22.
24" RCP
LF
691.5
$25.75
$17,806.13
24.
30" RCP
LF
139.5
$32.00
$4,464.00
JUSTIFICATION
The purpose of this change order is to bring the bid quantities to actual
constructed quantities and contract time to actual completion dates. The asphalt
pavement was eliminated because the tapers were paved with concrete instead. Extra dirt
was excavated to remove soft soil under the roadway. The 7" P.C. concrete pavement
and 4" Type V aggregate base quantities were larger due to a driveway that was added to
the project after the construction had begun. The additional contract time was granted to
the Contractor due to a request made by the City after the roadway was completed but the
project had not been finalized administratively. Residents downstream of a storm sewer
outlet requested that the City consider extending the pipe constructed with the roadway
project to an existing storm sewer in front of their homes after a heavy rain event caused
flooding in their backyards. The Contractor agreed to install the additional piping as a
change order to their original contract; however, a time adjustment was not made with
that change order.
CHANGE TO CONTRACT PRICE
Original contract price:
$552,679.96
Current contract price as adjusted by previous change orders:
$673,955.14
Current contract price due to this change order will be increased by:
$ 14,848.70
The new contract price due to this change order will be:
$688,803.84
CHANGE TO CONTRACT TIME
Original contract time:
Substantial completion time — 180 calendar days - January 27, 2001
Final completion time — 210 days - February 26, 2001
Current contract time as adjusted by previous change orders:
No change
Current contract time due to this change order will be increased by:
312 calendar days
The new contract time due to this change order will be:
Substantial completion — December 5, 2001
Final completion — January 4, 2001
APPROVALS REQUIRED:
To be effective, this Change Order must be approved by the Owner if it changes
the scope or objective of the project, or may otherwise be required under the terms of the
Supplementary General Conditions to the Contract.
Recommended b C - Date
Mark-A.Lgter, City ngineer
Approved by
Gertis, Project Manager
Michael G. Miller, City Manager
Date /o p
Accepted byDate - ,? 6 - O Z
Fronabarger on reters, Inc.