HomeMy WebLinkAboutRes.2859.12-15-2014BILL NO. 14-193
RESOLUTION N0. (3 J� 9
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE AN AGREEMENT WITH J & S
CONSTRUCTION/DEMOLITION, FOR THE DEMOLITION
OF VARIOUS BUILDINGS, IN THE CITY OF CAPE
GIRARDEAU, MISSOURI
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE
GIRARDEAU, MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the
City of Cape Girardeau, Missouri, is hereby authorized to
execute an Agreement with J & S Construction/Demolition, for the
demolition of buildings located at 818 North Fountain Street,
550 South Hanover Street, 610 Terry Lane and 638 Terry Lane, in
the City of Cape Girardeau, Missouri. The Agreement shall be in
substantially the form attached hereto as Exhibit A, which
document is hereby approved by the City Council, with such
changes therein as shall be approved by the officers of the City
executing the same.
1A. - 11 GI R.4j�,,
-N - -D:. TED THIS DAY OF 2014.
p Y
' 'A -k ! u�
TliE UNION ti•'
AT
SAIL
AlAh U t &'k& "
Gayle L. Conrad, City Clerk
Harry E. Red ger, Mayor
DEMOLITION CONTRACT
This agreement, entered into thisL gday of L=/yl.�z2, 2014, by and between
the City of Cape Girardeau, Missouri, a Municipal Corporation, hereinafter referred to as
"City", J & S Construction/Demolition, 45 County Rd. 706, Matthews, MO. 63867,
hereinafter referred to as "Contractor."
In consideration of the mutual covenants contained herein and other good and
valuable consideration, City and Contractor agree as follows:
Contractor shall totally demolish the following buildings:
1.
818 North Fountain Street
a. Remove 1'/Z story wood frame residence with basement.
(Log cabin framework)
b. Remove large storage shed in the rear yard.
c. Remove top and fill cistern.
d. Remove the concrete driveway, front concrete steps and all concrete slabs
e Remove six (6) metal poles, two (2) metal clothes line poles and stone well.
f. Remove all footings and foundations from all of the structures and break up the
basement floor.
g. Bury the concrete and stone on the site with a minimum of 2 ft. of fill.
h. Remove all rubbish and debris. Haul to an approved land fill.
i. Fill, grade, seed and straw the site.
550 South Hanover Street
a. Remove 1 '/2 story wood frame residence with basement.
b. Remove sidewalk to front steps and all concrete slabs.
c. Remove footing and foundation and break up the concrete floor.
d. Demolish the concrete block garage and remove the concrete slab.
e. Bury the concrete on the site with a minimum of 2 ft. of fill.
f. Remove all rubbish and debris. Haul to an approved land fill.
g. Fill, grade, seed and straw site.
610 Terry Lane
a. Remove one (1) story wood frame residence.
b. Remove footing, foundation, front sidewalk, and rear concrete slabs.
c. Bury the concrete on the site with a minimum of 2 ft. of fill.
d. Remove all rubbish and debris. Haul to an approved land fill.
e. Fill, grade, seed and straw site.
638 Terry Lane
a. Remove one (1) story wood frame residence.
b. Remove footing and foundation, front and rear sidewalks and all concrete slabs.
c. Remove detached wood frame garage, footing and foundations.
d. Bury the concrete on the site with a minimum of 2 ft. of fill.
e. Remove all rubbish and debris. Haul to an approved land fill.
f. Fill, grade, seed and straw site.
2. All debris and rubbish shall be removed from the demolition site and deposited
at a site satisfactory to the City. All holes left by removal of the foundations shall be filled
with good dirt, free of debris, and compacted to a density equal to the surrounding ground.
Dirt required for filling any holes shall be obtained at a site satisfactory to the City Engineer.
Contractor will be responsible for any damage done to the sidewalks, alleys or streets
adjoining the property. ,All utilities shall be disconnected prior to demolition. Contractor
shall take all necessary care to protect nearby buildings, drives, motor vehicles, and all
adjoining property, and the Contractor is to leave same in condition equal to that which now
exists.
3. Contractor shall provide all labor and materials, and furnish and direct at its
own expense, whatever equipment or work may be necessary for the expeditious and
proper execution of its duties under this contract.
4. Contractor shall secure, at its own expense, all permits, licenses and
consents required by law or necessary to perform this work and will give all notices and pay
all fees and otherwise comply with applicable city, county and state laws, ordinances, rules
and regulations. -
5. Should Contractor at any time refuse or neglect to supply adequate materials
or equipment or a sufficient number of properly skilled workmen, or fail in any respect to
prosecute the work with promptness and diligence, or fail to perform any of the agreements
of this contract, City may, at its election, immediately terminate this agreement, giving
notice to Contractor in writing of such election, and enter on the premises and take
possession for the purpose of completing the work included under this agreement, and
may employ any other person or persons to finish the work and to provide the materials
therefor at the expense of Contractor.
6. Contractor shall indemnify City from all claims, demands, suits and actions of
every name and description brought against the City for or on account of any injuries or
damages received or sustained by any parties by or as a result of the acts or omission of
- 2 -
Contractor, his servants or agents, in doing the work herein described, or by or as a result
of any negligence in guarding the same, or on account of any improper equipment or
materials utilized in performing the work.
7. Contractor shall prior to commencing work furnish to City a certified check or
a surety bond, the form of the bond and surety company to be approved by the City, in the
amount of Thirteen Thousand Four Hundred Ten Dollars ($13,410.00), conditioned on the
performance by Contractor of all its duties hereunder.
8. Contractor agrees to file with the City prior to commencement of work, a
certificate of insurance naming the City as coinsured and showing that the Contractor has
in force for a period equal to the period of the contract a policy of general liability insurance
insuring Contractor against liability for personal injuries and property damage arising out of
the contract in a minimum amount of $100,000.00 for injury or damage to any one person
and $2,000,000.00 for injuries or damages received in any one accident. Contractor
agrees to provide and maintain during the entire term of the contract and until final
acceptance of the -work by the City, workers compensation insurance for all of its
employees at the site of the work.
9. Upon satisfactory performance by Contractor of its duties under this contract,
and acceptance of said work by the City Engineer, City will pay Contractor the sum of
Thirteen Thousand, Four Hundred Ten Dollars ($13,410.00).
10. Time is of the essence of this agreement and Contractor agrees to begin
working within ten (10) days after the date of this contract and to complete the work within
forty-five (45) days, and in case the contract is not completed within this length of time,
excepting extensions granted to the Contractor for delays caused by conditions beyond his
control, Contractor will pay the City for damages the sum of Fifty Dollars ($50.00) per day
for each day over forty-five (45) days it is required to complete the work covered under this
contract.
11. Contractor shall not assign or sublet this contract or any portion thereof
without the prior written consent of the City.
12. Failure of the City to insist in any one or more instance on a strict
performance of all of the terms or conditions of this contract, or to exercise any right herein
contained, shall not be construed as a future waiver or a relinquishment of the provisions or
rights, but the same shall continue and remain in full force and effect. None of the terms or
conditions of this contract shall be altered, waived, modified or abandoned in any manner
except by written instrument executed by both parties.
- 3 -
I
Girar au,°Missouri
7F
W
EREOF, the parties have executed this agreement at Cape
y and year first above written.
CITY OF E GIF ARDEAU, MISSOURI
Gayle L. Conrad, City Clerk
ATTEST:
[Typed Name of Secretary]
A. M
er
J & S Construction/Demolition
Thomas Jones.
[Typed Name of Signer]