HomeMy WebLinkAboutRes.2841.09-22-2014BILL NO. 14-153
RESOLUTION NO. (!�
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE SUPPLEMENTAL AGREEMENT NO. 2, WITH
CRAWFORD, MURPHY, AND TILLY, INC., FOR THE
CONSTRUCTION PHASE SERVICES EXTENSION
REGARDING THE CONSTRUCTION OF T -HANGARS AT
THE CAPE GIRARDEAU REGIONAL AIRPORT
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF CAPE
GIRARDEAU, MISSOURI, AS FOLLOWS:
ARTICLE 1. The City Manager, for and on behalf of the City
of Cape Girardeau, Missouri, is hereby authorized to execute
Supplemental Agreement No. 2,with Crawford, Murphy, and Tilly,
Inc., for the construction phase services extension regarding
the construction of T -Hangars at the Cape Girardeau Regional
Airport, in the City of Cape Girardeau, Missouri. The Agreement
shall be in substantially the form attached hereto as Exhibit A,
which document is hereby approved by the City Council, with such
changes therein as shall be approved by the officers of the City
executing the same.
PASSED AND ADOPTED THIS DAY OF 2014.
Harry E. Rediger, Mayor
ATTEST:
Gayle . Conrad, City Clerk
Airport Name: Cape Girardeau Regional Airport
Project No.: 12-077A-1
County: Scott
AVIATION PROJECT CONSULTANT SUPPLEMENTAL AGREEMENT NO. 2 -
CONSTRUCTION PHASE SERVICES EXTENSION
THIS SUPPLEMENTAL AGREEMENT NO. 2 -CONSTRUCTION PHASE
SERVICES EXTENSION is entered into by the City of Cape Girardeau (hereinafter,
"Sponsor") and Crawford, Murphy & Tilly, Inc. (hereinafter, "Consultant").
WITNESSETH:
WHEREAS, the Sponsor and the Consultant entered into an Agreement on
September 1, 2011, to accomplish a project at the Cape Girardeau Regional Airport,
(hereinafter, "Original Agreement"); and
WHEREAS, the Sponsor and the Consultant entered into Supplemental
Agreement No.1 on July 3, 2013, to otherwise complete, extend or continue the Original
Agreement as provided herein.
WHEREAS, additional drainage work was added to the project which required
additional effort by the consultant.
WHEREAS, the Sponsor and the Consultant now desire to enter into
Supplemental Agreement No. 2 -Construction Phase Services Extension to otherwise
complete, extend or continue the Original Agreement.
NOW, THEREFORE, in consideration of the mutual promises, covenants, and
representations contained herein the parties agree as follows:
(1) SCOPE OF SERVICES:
(A) The Services to be provided by the Consultant under
Supplemental Agreement No. 2 -Construction Phase Services Extension are extensions
of the scope of services originally provided in the Supplemental Agreement No.1-
Construction Phase Services. These additional professional services are generally
described and defined in Section (17) of the Original Agreement and Exhibit II — SA1.
(2) FEES AND PAYMENTS:
(A) The Consultant shall be reimbursed in accordance with Section (9)
of the Original Agreement.
(B) The costs of Supplemental Agreement No. 2 -Construction Phase
Services Extension shall be in addition to the cost of the Original Agreement.
(C) The lump sum fee and maximum amount payable included in
Section (9) of the Original Agreement shall remain the same as follows:
Design & Bidding Phase Services
Construction Phase Services
ORIGINAL AMOUNT
SUPPLEMENTAL
AGREEMENT NO. 1
TOTAL
Lump Sum
$27,668.62
$0.00
$27,668.62
Max. Fee Payable
$36,298.62
$0.00
$36,298.62
(D) For and in consideration of the Construction Phase Administration
Services rendered by Consultant, Owner shall pay Consultant direct salaries, overhead,
direct expenses, and subconsultant fees as specified in Section (9) of the Original
Agreement plus a fixed fee of $6,137.76 for a total not to exceed amount of $56,341.42.
(E) Estimated costs for the services in Supplemental Agreement No. 2
are defined in Exhibit IV - SA2 and Exhibit V - SA2, which are attached hereto and
incorporated herein by reference.
(3) ORIGINAL AGREEMENT: Except as otherwise modified, amended, or
supplemented by this Supplemental Agreement No. 2 -Construction Phase Services
Extension, the Original Agreement and the Supplemental Agreement No. 1 -Construction
Phase Services between the parties shall remain in full force and effect and the terms of
the Original Agreement and Supplemental Agreement No.1-Construction Phase
Services shall extend and apply to this Supplemental Agreement No. 2 -Construction
Phase Services Extension.
Construction Phase Services
ORIGINAL AMOUNT
SUPPLEMENTAL
AGREEMENT NO. 1
SUPPLEMENTAL
AGREEMENT NO. 2
TOTAL
Fixed Fee
$0.00
$ 5,723.40
$ 414.36
$ 6,137.76
Max. Fee
$0.00
$52,161.08
$4,180.34
$56,341.42
(E) Estimated costs for the services in Supplemental Agreement No. 2
are defined in Exhibit IV - SA2 and Exhibit V - SA2, which are attached hereto and
incorporated herein by reference.
(3) ORIGINAL AGREEMENT: Except as otherwise modified, amended, or
supplemented by this Supplemental Agreement No. 2 -Construction Phase Services
Extension, the Original Agreement and the Supplemental Agreement No. 1 -Construction
Phase Services between the parties shall remain in full force and effect and the terms of
the Original Agreement and Supplemental Agreement No.1-Construction Phase
Services shall extend and apply to this Supplemental Agreement No. 2 -Construction
Phase Services Extension.
IN WITNESS WHEREOF, the parties have entered into this Supplemental
Agreement No. 2 -Construction Phase Services Extension on the date last written below.
Executed by the Consultant this le day of 20
Executed by the Sponsor thiso?51' day of ip b� , 20 �.
CONSULTANT
By: Az i /e / X A�Pc)�6
Title:
ATTEST:
Title: L6wl-s OFFja:
a
Title: e .1 _7
ATTEST: f
By:� t0+�
By: —K"^ e L nr6
Title: r%��-
FXHIBIi IV SA
DERIVATION OF CONSULTANT PROJECT COSTS
CAPE GIRARDEAU REGIONAL AIRPORT
CAPE GIRARDEAU, MISSOURI
CONSTRUCT 10 -UNIT T -HANGAR AND ASSOCIATED PAVEMENTS
CONSTRUCTION PHASE SERVICES
DIRECT SALARY COSTS:
TITLE HOURS
Principal
Senior Project Engineer
Project Manager
Senior Engineer
Engineer
Senior Planner
Planner
Registered Land Surveyor
Senior Technician
Technician
Clerk/Secretary
Total Direct Salary Costs
LABOR AND GENERAL ADMINISTRATIVE OVERHEAD:
Percentage of Direct Salary Costs @
SUBTOTAL:
Items 1 and 2
PROFIT:
15 % of Item 3 Subtotal
RATE/HOUR COST ($)
$0.00
421.60
0.00
0.00
649.92
0.00
0.00
0.00
0.00
0.00
0.00
= $1,071.52
= $1,690.86
= $2,762.38
$414.36 Fixed Fee
Subtotal $3,176.74
OUT-OF-POCKET EXPENSES:
a. Mileage
Miles @
$0 55 /Mile =
$523.60
b. Meals
Days @
$32 00 /Day =
$0.00
c. Motel
Nights @
$80.00 / Night=
$80.00
d. Nuclear Density Gage
Days @
$40 00 /Day =
$0.00
e. Printing and Shipping
=
$400.00
Total Out -of -Pocket Expenses
= $1,003.60
SUBCONTRACT COSTS:
a Bowen Soil, ,Aggregate PCC Testing
=
$0 00
b TSI Engineering. Inc Asphalt Testing
=
$0 00
c
=
$000
d
=
$000
_ $0.00
MAXIMUM TOTAL FEE:
Items 1, 2, 3, 4, 5 and 6
= $4,180.34 Not to
Lxhihit IV - SA2 I
EXHIBIT IV - SA 2
DERIVATION OF CONSULTANT PROJECT COSTS
CAPE GIRARDEAU REGIONAL AIRPORT
CAPE GIRARDEAU, MISSOURI
CONSTRUCTION PHASE SERVICES
Out -of -Pocket Expenses
Item
Max No. of People
Meals
Miles
Preconstruction Conference
2
0
0
Onsite Observation
1
0
0
Final Inspection
2
0
0
Punch List Verification
1
0
952
TOTAL =
0
952
Exhibit IV - SA2 - 2
CAPE GIRARDEAU REGIONAL AIRPORT
CAPE GIRARDEAU, MISSOURI
CONSTRUCTION PHASE SERVICES
CONSTRUCT 10 -UNIT T -HANGAR AND ASSOCIATED PAVEMENTS
Classification:
Gross Hourly Rate:
Principal
$211.68
Senior Project
Engineer
$156.24
Project
Manager
$123.24
Senior
Engineer
$96.00
Engineer
$80.28
Senior
Planner
$89.71
Planner
$75.13
Registered
Land Surveyor
$110.29
Senior
Technician
$95.64
Technician
$71.16
Clerk/
Secretary
$54.05
Other
Costs
CONSTRUCTION PHASE SERVICES
epart� comes m ountispacs •. o, sae �.< � actor purno-or.rnxoa�
,c vcloo r.Or' ��:Icmrnance won MoCov1 nv��nrr,F n.
a.le,m row m,aur I rneconsu.�c. ur., � � e e�N.e .,.x. n ,v�nwe �r�„me,
A.,vir�w �.�,ut, ,,,nom nalr,ial ,.unncanoi+`
�Oui 'u� a week
.,unSu iA UC'r UUSe�vauo�r ��� adv ..3VweeK
Ads s� Ike NE ar Inr 512n et K:'Y N'OI C t'.I C.o11 1 .11
yeSpO�d IO IieIC i55ue51llrpu JdOul dur3upn al pia IPC
'
Resp Io I-eoDOT questions n,puq�orn ou�atin„ nl p �ic�
'�epAr� (,onlrLetor 5 proyreas evi�male-
repave rna,roe prde•s and sriopkmernal agreemenrc nr,lwiro ICP
-
Plle,w c— --o tiiral ii sprrupi.
. enly .., mpleugn al pun.. 1151 icnndu�'latl q, Itk
�
•epaiH n,w su.t��rl isir: u,d rl,awiu,l`.
Rrnprre alw srrpmit Fi,�al li�ylinq Hepq�'
11 -de MuDU Nor all Cbsequl dp(: imenl .
32
0
8
0
0
24
0
0
0
0
0
0
Total hours =
$0.00
$1,926.82
$0.00
$0.00
$0.00
$0.00
1 $0.00
1 $0.00
1$1,003.60
To $4,180.341
$0.00
1 $1,249.92
$0.00
GRAND TOTAL = $41180.34
(1) Mileage, Motel and Meals (3) Computer Services (5) Printing and Shipping
(2) Equipment, Materials and Supplies (4) Vendor Services